Ikusasa Grain Mills Business Plan — Funding Structure & Use of Funds

8-year term; approximately 11.5% fixed; 12-month capital moratorium; secured over plant, silos and cession of debtors

Funding Structure & Use of Funds

Jump to section
Figure 14. Funding structure — the grant portion is what makes a thin-margin mill serviceable.

Source

Amount

Terms (indicative)

Senior term loan

R16.0m

8-year term; approximately 11.5% fixed; 12-month capital moratorium; secured over plant, silos and cession of debtors

Blended finance grant

R14.0m

IDC agro-processing / Land Bank blended finance; grant portion applied to fixed plant and infrastructure

Sponsor equity

R10.0m

Cash from founders, the producer co-operative and Motswedi Agri Capital, plus vendor-financed trust participation

Working capital facility

R8.0m

Revolving facility against grain stock and debtors; drawn seasonally around harvest

Total project

R48.0m

StrengthThe grant portion is essential rather than opportunistic, and the Plan proves it arithmetically

A milling business earns approximately R695 of contribution per tonne processed. At 14,400 tonnes a year that is R10.0 million of gross contribution before overheads. A R30 million commercial loan against that cash flow would not service, the arithmetic simply does not work, which is precisely why very few new independent mills are built on purely commercial terms. The blended grant portion reduces the debt to R16.0 million, which the milling margin can genuinely carry at cover approaching 2.0 times by Year 3. That is the market failure agro-processing blended finance exists to correct, and the Plan states the case in exactly those terms rather than treating the grant as a windfall. Without it this project should not proceed; with it, it is a sound credit.

11.1 Use of funds

Figure 15. Capital budget: R48.0 million.

Application

Amount

Milling plant and equipment (3 t/h degerming line)

R15.5m

Working capital (grain stock and debtors)

R9.5m

Buildings, warehouse and civils

R7.3m

Silos, intake handling and weighbridge

R6.2m

Electrical reticulation, MCC and standby generator

R3.1m

Packaging and fortification line

R2.4m

Vehicles and materials handling

R2.0m

Development, professional fees and contingency

R2.0m

Total

R48.0m

The allocation is well judged. Unlike several comparable plans, this one carries an explicit contingency line within development and professional fees, and it allocates R9.5 million, nearly a fifth of the project, to working capital, correctly recognising that a grain business consumes cash into stock and debtors long before it generates it.