Jive Monate Tavern & Shisanyama Business Plan — Implementation Roadmap

The programme runs across three phases over 84 months, sequenced so that a profitable, well-run flagship is established before any expansion. The critical…

Implementation Roadmap

Jump to section

The programme runs across three phases over 84 months, sequenced so that a profitable, well-run flagship is established before any expansion. The critical path runs through funding and lease → liquor licence and municipal approvals → property improvements and venue build-out → kitchen, bar, security and power installation → staffing and training → grand opening → footfall and reputation build → cumulative break-even → events, VIP and corporate growth → a proven, cash-generative flagship → expansion.

Figure 13. Implementation Gantt: critical milestones, timelines and dependencies.

Phase plan and milestones

Phase

Focus

Key milestones

Window

Phase I

Build & launch

Licence; build-out; grand opening

Months 0–12

Phase II

Establish & grow

Break-even (~M22); VIP, events & corporate

Months 12–48

Phase III

Expand

Proven flagship; second & third venues

Months 48–84

Critical dependencies

Dependency

Gates

Mitigation

Liquor licence approval

All trading

Early application; specialist advisors

Site lease & zoning

Build-out start

Pre-agreed lease; zoning confirmed

Property improvements & fit-out

Opening date

Fixed-price contract; contingency

Equipment delivery & installation

Kitchen & bar readiness

Early ordering; supplier SLAs

Recruitment & training

Service quality at launch

Recruit from month 10; structured training

Backup power & security

Safe, reliable trading

Installed & tested pre-opening

Analyst flagThe liquor licence is the gating item on the critical path

Four dependencies gate the launch, and one dominates. The liquor licence and municipal approvals must be secured before the venue can trade, no licence, no business, and licensing timelines in South Africa can be lengthy and unpredictable. The roadmap therefore starts the licence application early and runs it in parallel with the build. The other three dependencies are securing the right high-visibility Mamelodi East site; completing property improvements and installing kitchen, bar, security and backup power; and recruiting and training a 24-person team before opening. Funders should treat licence approval as a condition precedent to drawdown of construction capital.