Lichtenburg Nut Company Business Plan — Capital Expenditure

The plant and equipment programme, its phasing, and what each tranche of capital buys.

Section 26 of 37

Capital Expenditure

Jump to section
Process plant absorbs 60% of the R105 million Phase 1 programme
Figure 1. Process plant absorbs 60% of the R105 million Phase 1 programme

25.1 Phase 1 schedule

Table 56. Phase 1 capital expenditure schedule (R’000)

Item

Cost (R’000)

Book life

Tax treatment

Leasehold improvements, food-grade fit-out and civils

13,800

15 years

s11(g), over lease term

Groundnut intake, drying, shelling, grading and aerated storage

11,200

12 years

s12C, 40/20/20/20

Roasting, blanching, colour sorting and two-stage milling line

21,000

12 years

s12C, 40/20/20/20

Homogenising, de-aeration, scraped-surface chilling, tanks and CIP

7,600

12 years

s12C, 40/20/20/20

Retail filling, capping, labelling and case packing line

10,400

10 years

s12C, 40/20/20/20

Bulk pail, drum and IBC filling station

3,000

10 years

s12C, 40/20/20/20

Laboratory and aflatoxin testing suite (HPLC, ELISA, microbiology)

3,600

8 years

s12C, 40/20/20/20

Utilities: dual-fuel roaster energy, steam, chilling, compressed air, MV/LV reticulation, 250 kWp PV and standby generation

9,400

15 years

s12C, 40/20/20/20

Fire detection and suppression, effluent and food-safety infrastructure

1,900

15 years

s12C, 40/20/20/20

Materials handling equipment, racking and pallets

2,300

8 years

s11(e) wear and tear

IT, ERP, batch traceability and warehouse management systems

1,900

4 years

s11(e) wear and tear

Light delivery and site vehicles

1,150

5 years

s11(e) wear and tear

Installation, engineering, project management and commissioning

5,600

12 years

s12C, 40/20/20/20

Pre-operating: recruitment, training, FSSC 22000 certification, product development, trial production and market entry

5,600

5 years

s11A on commencement of trade

Contingency (7% of hard cost)

6,500

12 years

s12C, 40/20/20/20

Total Phase 1

104,950

Buildings are leased rather than purchased, avoiding an estimated R28 million of capital in exchange for rental of approximately R3.9 million a year at Year 5. This improves return on invested capital at the cost of a permanent operating expense.

25.2 Phases 2 and 3, and maintenance capital

Table 57. Phase 2, Phase 3 and maintenance capital

Phase

Timing

Content

Cost

Funding

Phase 2

Months 37 to 42 (Operating Year 3)

Snack roasting, seasoning, multihead weighing and vertical form-fill-seal packing line; warehouse extension of 800 m²; additional silo, intake and chilled holding capacity

R17.3m

Operating cash flow and the revolving facility

Phase 3

Months 73 to 78 (Operating Year 6)

De-bottlenecking of the roasting and milling train from 3,400 t to 4,800 t nameplate

R31.3m

Committed R30m expansion tranche drawn in month 74

Maintenance capital

From Operating Year 3, ongoing

1.5% of gross property, plant and equipment per annum

R1.8m in FY2033

Operating cash flow

Table 58. Capital expenditure and the asset base

R million unless stated

FY2028

FY2029

FY2030

FY2031

FY2032

FY2033

Phase capital expenditure

105.0

0.0

0.0

17.3

0.0

0.0

Maintenance capital expenditure

0.0

0.0

0.0

1.8

1.8

1.8

Total capital expenditure

105.0

0.0

0.0

19.1

1.8

1.8

Gross property, plant and equipment

105.0

105.0

105.0

124.0

125.9

127.7

Net property, plant and equipment

104.3

94.4

84.5

92.8

82.9

73.4

Depreciation charge

0.6

9.9

9.9

10.8

11.7

11.4