Magalies Quarry Business Plan — Risk Analysis

Demand cyclicality, plant availability, regulatory and geological risk, with controls and trigger points.

Section 16 of 26

Risk Analysis

Jump to section

Risks are prioritised, not merely listed; demand, pricing and permitting sit at the top, each with a defined mitigation and owner.

Residual risk heat map after mitigation (see register for R1–R12)
Figure 1. Residual risk heat map after mitigation (see register for R1–R12).

Risk register

#

Risk

P

I

Mitigation

Owner

R1

Demand / construction cycle

Med

Maj

Anchor offtake; flexible cost base; staged capex

GM

R2

Selling-price pressure

Med

Maj

Delivered-cost discipline; mix toward higher value

Sales

R3

Permitting / regulatory delay

Low

Maj

Early, resourced permitting; expert advisors

GM/SHEQ

R4

Ramp / commissioning

Med

Mod

Staged commissioning; reputable EPC; contingency

Plant

R5

Power cost & reliability

High

Mod

Efficient plant; standby power; tariff management

Plant

R6

Diesel & input inflation

High

Min

Price escalation; efficiency; supplier contracts

Finance

R7

Key-equipment failure

Low

Mod

Maintenance regime; critical spares; warranties

Plant

R8

Environmental / water

Low

Maj

EMPr compliance; water recycling; monitoring

SHEQ

R9

Community relations (SLP)

Med

Mod

Local employment/procurement; engagement forum

GM

R10

FX on imported spares

Med

Min

Local sourcing where possible; forward cover

Finance

R11

Interest-rate / refinancing

Med

Mod

DSRA; hedging; deleveraging plan

Finance

R12

Skills / labour

Med

Min

Training; competitive terms; contractor flex

GM

The risk that matters most

The dominant risk is a sustained construction downturn that compresses volume and price together. The scenario analysis quantifies this explicitly: in the downside case, committed liquidity is exhausted and equity value is impaired. Mitigation is structural, conservative gearing, a debt-service reserve, a revolving facility, staged capital and, for a genuine downside, a standby equity commitment from shareholders able to provide it.