Magalies Quarry Business Plan — Strategic Plan

Strategic objectives across the five years and the sequencing of capacity, product mix and market reach.

Section 14 of 26

Strategic Plan

Jump to section

Where to play: the corridor’s higher-value stone and manufactured-sand demand. How to win: lowest delivered cost, compliant quality, reliable supply.

Three-to-five-year objectives

  1. Commission Phase 1 and achieve first product within roughly 20 months of financial close.
  2. Secure one to two anchor offtake accounts before commissioning to underpin base-load volume.
  3. Complete Phase-2 debottlenecking to reach 720 kt nameplate capacity by Years 2–3.
  4. Establish accredited-supplier status for manufactured sand and G-materials with major buyers.
  5. Deleverage to below 2x net debt/EBITDA by Year 4 and build a track record for a value-accretive exit or refinancing.

Where to play / how to win

Where to play

How to win

Capabilities required

Corridor ready-mix & asphalt

Lowest delivered cost + consistent grading

Efficient plant, QA lab, reliable dispatch

Road rehabilitation & civils

Full G-material range, reliable volumes

Layerworks production, logistics

Manufactured-sand substitution

Compliant sand at scale

VSI sand plant, washing/classification, accreditation