Midrand Print Company Business Plan — Risk Analysis

Digital substitution, overcapacity, input cost and credit risk, with controls and trigger points for each.

Section 17 of 28

Risk Analysis

Jump to section

16.1 Risk register

Risk

Prob.

Impact

Rating

Mitigation

Owner

R1

Volume shortfall against the account acquisition plan

High

High

Critical

Paid pilot model to shorten and de-risk conversion; second press deferrable to FY2031 on single-press capacity; expansion capex gated on utilisation triggers rather than calendar

MD

R6

Ramp-phase debt-service gap before FY2030

High

High

Critical

Twelve-month capital moratorium on AF1; 18-month moratorium on the term loan; covenant testing deferred to the FY2030 measurement date; R7.5m revolver as the liquidity buffer

FM

R2

Working-capital absorption and debtor stretch

High

Medium

High

Credit limits set before first order; consolidated monthly programme billing; credit insurance on the ten largest exposures from FY2029; debtor days a board KPI and a bonus metric

FM

R3

Loss of an anchor account

Medium

High

High

No single account above 12% of revenue by policy; annual contracts with 90-day notice; embedded template libraries raise switching cost

Head of Programmes

R4

Substrate cost inflation and rand volatility

High

Medium

High

Dual-sourced substrate by category; quarterly rate-card review; currency adjustment clause above a 7% movement threshold

Ops Director

R11

Structural decline in print demand

High

Medium

High

Portfolio weighted to branch, regulatory and in-store collateral with no digital substitute; service revenue growing as a share of the mix

MD

R5

Press downtime and unplanned maintenance

Medium

High

High

OEM service contract with response-time commitment; capacity headroom allows rescheduling; trade-finisher relationships provide overflow

Ops Director

R7

Power supply interruption

High

Low

Medium

Backup capable of carrying a controlled shutdown; production scheduled around published load curtailment where possible; cost provided in overheads

Ops Director

R8

Scarcity of skilled press operators

Medium

Medium

Medium

Structured apprenticeship with the OEM; retention premium budgeted into production labour; cross-training across lines

Ops Director

R9

Technology obsolescence of the installed base

Low

High

Medium

Seven-year asset lives against a six-to-eight year practical technology cycle; maintenance and upgrade capex provided from FY2029

Ops Director

R10

Regulatory, environmental and B-BBEE compliance

Low

Medium

Low

ISO 9001 and FSC certification in months 5–11; B-BBEE verification annually; waste and solvent handling to permit conditions

FM

R12

Key-person dependency

Medium

Medium

Medium

Documented programme and scheduling procedures; deputy identified for each critical role by FY2029; key-person cover on the two founder executives

Board

Table 28: Risk register, ordered by overall rating

16.2 Risk heat map

Two risks sit in the critical quadrant — and they are the same commercial exposure seen twice
Figure 1. Two risks sit in the critical quadrant — and they are the same commercial exposure seen twice

R1 and R6 are not independent. The debt-service gap exists because the fixed cost base and the financing structure are sized for the volume plan; if volume arrives, the gap closes on schedule. Treating them as two risks with two mitigations overstates the diversification in the register. The honest formulation is that this is a single-factor risk case: the company is exposed to whether it can acquire and hold programme accounts at the modelled rate, and almost everything else in the register is second-order beside it.