PowerWorks Force Green Energy Business Plan — Appendix B: Assumptions & Capex Register

B.1 Capital cost & depreciation register Asset category Cost (R million) Useful life (years) Solar modules 640 25 Battery storage system 420 12 Electrical…

Appendix B: Assumptions & Capex Register

Jump to section

B.1 Capital cost & depreciation register

Asset category

Cost (R million)

Useful life (years)

Solar modules

640

25

Battery storage system

420

12

Electrical balance of plant

230

25

Mounting structures

180

25

Inverters

170

15

Transmission interconnection

150

25

EPC costs

150

25

Land acquisition & development

120

25

Contingency

100

25

Development, permits & engineering

90

25

Working capital

20

—

Total project cost

2,270

Item

Provision (R million)

Interest during construction (IDC)

204

Debt service reserve account (6 months)

125

BESS augmentation reserve (initial funding)

60

Total additional provision

389

Revised funded project cost

2,659

B.3 Key assumptions register

Parameter

Assumption

Revenue (preserved)

R610m → R723m over five years

EBITDA (preserved)

R470m → R570m (77.0% → 78.8%)

Annual generation

295 GWh; degradation 0.5% p.a. from year 6

Implied blended tariff

R2.07/kWh Year 1 (reconciled range R1.50–1.70)

Operating cost

R140m Year 1, escalating 5.5% p.a.

Senior debt

R1.70bn at 12%, 15-year level amortisation

Sponsor equity

R570m (25% of project cost)

Corporate tax

27% with Section 12B (50/30/20); 80% loss set-off cap

Replacement capex

BESS R330m ~year 12; inverters R140m ~year 15

Merchant tail

Years 21–25 at 72% of contracted pricing

Repo / prime (SARB, mid-2026)

7.0% / 10.5%