PowerWorks Force Green Energy Business Plan — Construction, EPC & Procurement
Construction is programmed at eighteen months from EPC mobilisation, with two months of testing and commissioning, delivering commercial operation within…
Construction, EPC & Procurement
Jump to section
- Overview & contents
- Important Notice & Confidentiality
- Executive Summary
- Company Overview, Vision & Governance
- Industry & Market Analysis
- Market Sizing & Offtake Opportunity
- Competitive Landscape & Positioning
- Project Description & Technology
- Revenue Model & Offtake Strategy
- Operations, Maintenance & Asset Management
- Grid Connection & Transmission Access
- Development Programme & Permitting
- Construction, EPC & Procurement
- Implementation Roadmap
- Management, Board & Governance
- Environmental, Social & Governance
- Financial Plan & Projections
- Funding Requirement & Capital Structure
- Returns, Scenarios & Sensitivity
- Risk Analysis & Independent Findings
- SWOT & Investment Thesis
- Appendix A: Detailed Financial Statements
- Appendix B: Assumptions & Capex Register
- Appendix C: Glossary & Methodology
Construction is programmed at eighteen months from EPC mobilisation, with two months of testing and commissioning, delivering commercial operation within thirty-six months of financial close. The intended contracting approach, a fixed-price, date-certain engineering, procurement and construction contract with performance guarantees, is the correct structure and is what lenders require.
Construction risk allocation
|
Risk |
Allocation |
Instrument |
|---|---|---|
|
Cost overrun |
EPC contractor |
Fixed-price lump-sum contract |
|
Delay |
EPC contractor |
Date-certain completion; delay liquidated damages |
|
Performance shortfall |
EPC contractor |
Performance guarantees and performance LDs |
|
Contractor default |
Lenders / sponsor |
Performance bond; retention; parent guarantee |
|
Ground conditions |
Shared |
Geotechnical survey; defined allowance |
|
Force majeure |
Shared |
Contractual relief; construction all-risks insurance |
Procurement and foreign exchange
The sponsor indicates that equipment will be procured from a reputable supplier in China, a sensible commercial decision given that Chinese manufacturers dominate global module, inverter and battery supply and offer the most competitive pricing. It carries a specific financial consequence, however, that the plan does not currently address. Modules, inverters and battery systems together account for approximately R1.23 billion of the R2.27 billion capital cost, and this equipment is priced in United States dollars or Chinese yuan. Between the fixing of the project budget and the payment of supplier milestones, the rand exposure on that portion of the capital cost is unhedged unless deliberately managed.
Roughly R1.23 billion of the capital budget, modules, inverters and the battery system, is effectively denominated in foreign currency. A ten percent rand depreciation between budget approval and payment would add approximately R123 million to project cost, which exceeds the entire R100 million contingency provision. Standard practice is to fix the exchange rate through forward cover taken at or shortly after financial close, matched to the EPC payment schedule, with the cost of that cover built into the budget. The plan should also confirm import duties, tariff classifications and any local-content requirements applicable under the relevant procurement framework, since these affect both landed cost and eligibility for certain programmes.