PowerWorks Force Green Energy Business Plan — Construction, EPC & Procurement

Construction is programmed at eighteen months from EPC mobilisation, with two months of testing and commissioning, delivering commercial operation within…

Construction, EPC & Procurement

Jump to section

Construction is programmed at eighteen months from EPC mobilisation, with two months of testing and commissioning, delivering commercial operation within thirty-six months of financial close. The intended contracting approach, a fixed-price, date-certain engineering, procurement and construction contract with performance guarantees, is the correct structure and is what lenders require.

Construction risk allocation

Risk

Allocation

Instrument

Cost overrun

EPC contractor

Fixed-price lump-sum contract

Delay

EPC contractor

Date-certain completion; delay liquidated damages

Performance shortfall

EPC contractor

Performance guarantees and performance LDs

Contractor default

Lenders / sponsor

Performance bond; retention; parent guarantee

Ground conditions

Shared

Geotechnical survey; defined allowance

Force majeure

Shared

Contractual relief; construction all-risks insurance

Procurement and foreign exchange

The sponsor indicates that equipment will be procured from a reputable supplier in China, a sensible commercial decision given that Chinese manufacturers dominate global module, inverter and battery supply and offer the most competitive pricing. It carries a specific financial consequence, however, that the plan does not currently address. Modules, inverters and battery systems together account for approximately R1.23 billion of the R2.27 billion capital cost, and this equipment is priced in United States dollars or Chinese yuan. Between the fixing of the project budget and the payment of supplier milestones, the rand exposure on that portion of the capital cost is unhedged unless deliberately managed.

Analyst flagForeign-exchange exposure on imported equipment requires an explicit hedging strategy

Roughly R1.23 billion of the capital budget, modules, inverters and the battery system, is effectively denominated in foreign currency. A ten percent rand depreciation between budget approval and payment would add approximately R123 million to project cost, which exceeds the entire R100 million contingency provision. Standard practice is to fix the exchange rate through forward cover taken at or shortly after financial close, matched to the EPC payment schedule, with the cost of that cover built into the budget. The plan should also confirm import duties, tariff classifications and any local-content requirements applicable under the relevant procurement framework, since these affect both landed cost and eligibility for certain programmes.