PowerWorks Force Green Energy Business Plan — Grid Connection & Transmission Access

This section addresses what the analysis identifies as the project’s single greatest risk. It is treated separately, and at length, because in the current…

Grid Connection & Transmission Access

Jump to section

This section addresses what the analysis identifies as the project’s single greatest risk. It is treated separately, and at length, because in the current South African market grid access, not solar resource, not technology, not even offtake, determines whether a renewable project is financeable.

The national position

Eskom’s Generation Connection Capacity Assessment, published to inform independent power producers of available transmission capacity, confirmed that the Northern Cape has effectively no remaining generation connection capacity. The province’s grid was absorbed by earlier REIPPPP bid windows, the risk mitigation procurement programme and privately contracted projects. The consequences have been concrete: in Bid Window 6 no wind projects were selected at all, because the available capacity in the strongest resource areas had already been allocated. Transmission has since been separated into the National Transmission Company of South Africa, and every new project must be accommodated within long-term grid planning that begins from these existing constraints.

Competition for the remaining capacity has become adversarial. In a dispute that reached the High Court, a developer challenged the cancellation and reallocation of 240 MW of previously allocated grid access to publicly procured Bid Window 7 projects, obtaining an interim interdict in December 2025 restraining Eskom and the National Transmission Company from using the disputed capacity pending final determination. Independent commentary in mid-2026 concluded that South Africa’s constraint has shifted from generation capacity to grid infrastructure, with allocation decisions now among the most contested factors shaping the energy transition.

Curtailment

Eskom has proposed introducing curtailment of approximately ten percent as a mechanism to release additional connection capacity, an addendum to the 2025 capacity assessment indicated that a ten percent curtailment regime could accommodate around 3,470 MW of additional wind capacity. For a project economics standpoint this is a double-edged development: it may be the mechanism by which a connection becomes available at all, but curtailment directly reduces energy delivered and therefore revenue, and curtailed volumes are generally not compensated. A ten percent curtailment applied to this project would reduce annual energy from 295 GWh to approximately 266 GWh, with a proportionate effect on revenue that flows almost entirely to EBITDA given the largely fixed cost base.

What must be evidenced

Requirement

Evidence needed

Timing

Cost estimate letter / budget quote

Issued by Eskom for the specific connection point

Development

Budget quote acceptance and payment

Proof of payment securing the allocation

Pre-financial close

Grid connection agreement

Executed, with defined connection date

Pre-financial close

Curtailment terms

Written curtailment regime and compensation basis

Pre-financial close

Self-build or Eskom-build scope

Defined responsibility and cost allocation

Pre-financial close

Transmission strengthening dependency

Confirmation project does not depend on unfunded upgrades

Pre-financial close

Analyst flagGrid access is the condition on which everything else depends

The sponsor lists ‘existing transmission infrastructure’ among its site-selection reasons and cites ‘secured grid capacity’ as its mitigation for grid connection risk. Given the documented position in the Northern Cape, that assertion cannot be accepted on its face. Financiers should require documentary evidence of a paid, accepted budget quote and an executed grid connection agreement, together with written terms governing curtailment, before committing capital. If firm capacity cannot be evidenced, no amount of resource quality, technology selection or financial structuring will make the project bankable, and the sponsor should consider alternative locations closer to load centres where capacity exists, accepting a modest reduction in irradiation in exchange for a connection that is actually available.