PowerWorks Force Green Energy Business Plan — Implementation Roadmap

The programme runs from project commencement through development, financial close, construction and commissioning to twenty-five years of operation. The…

Implementation Roadmap

Jump to section

The programme runs from project commencement through development, financial close, construction and commissioning to twenty-five years of operation. The critical path runs through grid capacity and environmental authorisation in the development phase, then through module, inverter and battery delivery and the substation interconnection during construction.

Figure 11. Implementation Gantt: development, construction and operations with critical milestones.

Phase plan and milestones

Phase

Focus

Key milestones

Window

Development

Grid, permits, offtake, financing

Financial close

Months 0–19

Construction

EPC delivery, installation, interconnection

Commercial operation date

Months 19–39

Operations

Generation, O&M, debt service, distributions

Debt fully repaid (year 15)

Months 39–339

Critical dependencies

Dependency

Gates

Mitigation

Firm grid capacity

Everything

Paid budget quote; connection agreement

Environmental authorisation

Construction start

Early EIA start; specialist studies in parallel

Signed PPAs with credit approval

Financial close

Diversified offtakers; credit support

NERSA licensing

Operation

Early application; regulatory counsel

Fixed-price EPC contract

Debt commitment

Competitive tender; bankable contractor

FX cover on imported equipment

Budget certainty

Forward cover at financial close

Substation & interconnection works

COD

Coordinate Eskom scope; early long-lead orders

Analyst flagFinancial close is the gate, and grid capacity is the gate to financial close

No senior debt will be committed until grid capacity, environmental authorisation, offtake and the EPC contract are all in place. The realistic development timeline to financial close is nineteen months rather than the shorter period the sponsor’s schedule implies, and the entire development budget, engineering, permits, legal, advisory and grid application costs of approximately R90 million, is at risk until close is achieved. Sponsors should be capitalised to fund this development phase from equity, and investors entering before financial close should understand that they are taking development risk, which is qualitatively different from the infrastructure risk they will hold afterwards.