PowerWorks Force Green Energy Business Plan — Management, Board & Governance

The founding team’s combination of development, financial and technical experience is well matched to a project of this scale, and the technical director’s…

Management, Board & Governance

Jump to section

The founding team’s combination of development, financial and technical experience is well matched to a project of this scale, and the technical director’s delivery record of more than 800 MW is a material credential in a market where execution capability is scarce.

Director

Role

Mandate & profile

Thabo Nkosi

Chief Executive Officer (38%)

Strategy, offtake origination, stakeholders; 18+ years infrastructure development

Lindiwe Naidoo

Finance Director (34%)

Project finance, lender relations, financial control; Chartered Accountant

Michael van der Merwe

Technical Director (28%)

Engineering, EPC, grid interface, performance; 800+ MW delivered

Governance under project finance

  • Board accountability for compliance with the common terms agreement, including financial covenants, reporting obligations, reserve account maintenance and distribution lock-up tests.
  • An independent engineer appointed by lenders to certify construction milestones and authorise drawdowns, and to review operating performance during the term.
  • A model auditor and independent insurance, legal, environmental and market advisers appointed as part of the lender due-diligence process before close.
  • Segregated project accounts under an account bank agreement, with a defined cash waterfall governing the order in which revenue meets operating costs, debt service, reserves and distributions.
  • Quarterly reporting to lenders and shareholders covering generation, availability, performance ratio, PPA compliance, coverage ratios and reserve balances.

Team gaps to address

Three capability gaps are worth noting. The first is an experienced asset manager to run the plant commercially after commercial operation, a role distinct from both construction management and corporate finance. The second is dedicated offtake origination and contract management capacity, since the commercial success of the project rests on concluding and then administering complex wheeling arrangements over twenty years. The third is health, safety, environment and community capability, which becomes significant during a construction phase employing approximately 300 people and is a continuing obligation under environmental authorisation conditions. These roles should be identified and, where possible, contractually committed before financial close.