Sable Grid Storage Business Plan — Annexure B: Assumptions Book

Structured on recent public storage procurement clearing levels; CPI-indexed

Annexure B: Assumptions Book

Jump to section

Assumption

Value

Source / rationale

Capacity tariff

R300k/MW/month

Structured on recent public storage procurement clearing levels; CPI-indexed

CPI escalation

5.0% p.a.

Mid-point of SARB target band, applied to revenue and opex

Availability

97.5% modelled

Above 97% guarantee; incentive band shares outperformance with offtaker

Round-trip efficiency

86%

AC-AC at point of connection, warranted; programme minimum 70%

Cycling

330 EFC p.a.

Within 365-cycle warranty envelope

Degradation

2.2% p.a. average

Managed to ≥95% contracted capacity via year 8/14 augmentation

EPC price

R1,770m fixed

Signed term sheet; ZAR-denominated with supplier FX hedging

Owner’s costs & IDC

R280m

Development, legal, advisory, insurance during construction, interest

Senior debt tenor / rate

15 yrs / 11.5%

All-in post-swap; DFI-anchored pricing indication

Senior debt service

R205m p.a.

Level amortisation; reconciles exactly to facility, rate and tenor

Mezzanine

R150m; ~R32m p.a. to year 8

Subordinated; funds community trust participation

Stated gearing / effective gearing

70:30 / 77:23

Effective figure treats mezzanine as debt

Opex year 1

R52m

LTSA R28m; insurance R9m; staff/admin R11m; land/rates R4m

Depreciation

20-year straight line

R2.05bn base; augmentation capitalised in years 8 and 14

Augmentation capex

R160m (Y8), R150m (Y14)

Funded from maintenance reserve; real battery prices declining

Tax rate

27%

Accelerated allowances modelled with and without relief

Contract term

15 years

Plus re-contracting tail years 16–20, excluded from base-case returns

Merchant tail assumption

55% of prior capacity payment

Conservative re-contracting assumption for years 16–20