Sable Grid Storage Business Plan — Annexure C: Scenario & Sensitivity Detail

The re-derived downside outcome is more severe than the sponsor’s estimate, approximately 9% against 11.9%, principally because the re-derivation applies…

Annexure C: Scenario & Sensitivity Detail

Jump to section

C.1 Scenario definitions and outcomes

Metric

Downside

Base

Upside

Capacity tariff

-10%

R300k/MW/month

+10%

Capex

+10%

R2,050m

-5%

Availability

95.0%

97.5%

98.5%

Merchant revenue

Zero

R14m Year 1

2× base

Equity IRR (from COD)

8.95%

20.7%

32.08%

Sponsor stated equity IRR

11.9%

19.8%

25.6%

C.2 Single-variable sensitivity (equity IRR, %)

Driver

Downside case

Base

Upside case

Capacity tariff +/-10%

16.0%

20.7%

26.7%

Capex +10% / -5%

17.3%

20.7%

23.7%

Availability 95.0% / 98.5%

19.9%

20.7%

22.0%

Debt rate 13.5% / 10.5%

18.7%

20.7%

22.7%

Accelerated tax allowance lost

18.5%

20.7%

20.7%

Merchant zero / 2x

19.3%

20.7%

23.5%

The re-derived downside outcome is more severe than the sponsor’s estimate, approximately 9% against 11.9%, principally because the re-derivation applies the stresses to a cash-flow-based model including mezzanine service and full reserve funding. The direction of the sponsor’s conclusion nonetheless holds: even under simultaneous adverse movements the senior debt continues to be serviced, and the covenant is not breached. The distinction that matters is between debt resilience, which the structure demonstrably has, and equity return adequacy, which under combined stress it does not.