Sable Grid Storage Business Plan — Construction, EPC & Procurement
Construction is programmed at eighteen months from financial close to commercial operation, delivered under a fixed-price, date-certain engineering,…
Construction, EPC & Procurement
Jump to section
- Overview & contents
- Important Notice & Confidentiality
- Executive Summary
- Company Overview & Governance
- Industry & Market Analysis
- Regulatory & Policy Environment
- Market Sizing & Demand Drivers
- Competitive Landscape & Positioning
- Products, Services & Revenue Model
- Project Sizanani, The Flagship Asset
- Technology & Engineering
- Grid Connection & Transmission Access
- Offtake Strategy & Counterparty Risk
- Construction, EPC & Procurement
- Operations, Maintenance & Asset Management
- Implementation Roadmap
- Financial Plan & Projections
- Funding Requirement & Capital Structure
- Returns, Scenarios & Sensitivity
- Risk Analysis & Independent Findings
- SWOT, PESTLE & Strategic Analysis
- Management Team & Organisation
- Transformation, Localisation & ESG
- Investor Returns, Exit & Conclusion
- Annexure A: Detailed Financial Statements
- Annexure B: Assumptions Book
- Annexure C: Scenario & Sensitivity Detail
- Annexure D: Development Pipeline
- Annexure E: Risk Register
- Annexure F: Glossary & Methodology
Construction is programmed at eighteen months from financial close to commercial operation, delivered under a fixed-price, date-certain engineering, procurement and construction contract with the Company’s technology partner as integrator. This is the correct structure for a project financing and is what lenders require.
12.1 Risk allocation
|
Risk |
Allocation |
Instrument |
|---|---|---|
|
Cost overrun |
EPC contractor |
Fixed-price lump-sum contract; 8% owner’s contingency |
|
Delay |
EPC contractor |
Date-certain completion; delay liquidated damages sized to debt service |
|
Capacity shortfall at commissioning |
EPC contractor |
Performance liquidated damages buying down the shortfall |
|
Contractor default |
Lenders / sponsor |
Parent company guarantee; 10% performance security |
|
Long-lead plant delay |
Shared |
Early ordering of transformers and 132 kV plant in early works |
|
Ground conditions |
Shared |
Geotechnical survey; defined allowance |
|
Force majeure |
Shared |
Contractual relief; construction all-risks insurance |
12.2 Procurement and currency
The Plan states that the engineering contract is priced in rand with supplier-side currency hedging, and that residual exposure is hedged at notice to proceed. This is a materially stronger position than the more common structure in which imported equipment is priced in dollars and the exposure sits with the project. Battery direct-current blocks are imported, there is no domestic manufacture at scale, while transformers, medium-voltage switchgear, cabling, civils and structural steel are procured locally, with assembly and commissioning labour localised.
In most South African renewable financings the largest single procurement risk is the currency movement between budget approval and equipment payment, because modules, inverters and batteries are dollar- or yuan-priced. A rand-denominated fixed-price contract with the contractor carrying the hedging obligation transfers that exposure to the party best able to manage it, and removes a common source of pre-completion cost escalation. Due diligence should nonetheless confirm the contractor’s own hedging arrangements and its balance-sheet capacity to absorb the exposure, since a fixed price is only as good as the counterparty standing behind it, which is precisely what the parent company guarantee and performance security are for.