Sable Grid Storage Business Plan — Construction, EPC & Procurement

Construction is programmed at eighteen months from financial close to commercial operation, delivered under a fixed-price, date-certain engineering,…

Construction, EPC & Procurement

Jump to section

Construction is programmed at eighteen months from financial close to commercial operation, delivered under a fixed-price, date-certain engineering, procurement and construction contract with the Company’s technology partner as integrator. This is the correct structure for a project financing and is what lenders require.

12.1 Risk allocation

Risk

Allocation

Instrument

Cost overrun

EPC contractor

Fixed-price lump-sum contract; 8% owner’s contingency

Delay

EPC contractor

Date-certain completion; delay liquidated damages sized to debt service

Capacity shortfall at commissioning

EPC contractor

Performance liquidated damages buying down the shortfall

Contractor default

Lenders / sponsor

Parent company guarantee; 10% performance security

Long-lead plant delay

Shared

Early ordering of transformers and 132 kV plant in early works

Ground conditions

Shared

Geotechnical survey; defined allowance

Force majeure

Shared

Contractual relief; construction all-risks insurance

Figure 11. Cumulative deployment of funds through to commercial operation.

12.2 Procurement and currency

The Plan states that the engineering contract is priced in rand with supplier-side currency hedging, and that residual exposure is hedged at notice to proceed. This is a materially stronger position than the more common structure in which imported equipment is priced in dollars and the exposure sits with the project. Battery direct-current blocks are imported, there is no domestic manufacture at scale, while transformers, medium-voltage switchgear, cabling, civils and structural steel are procured locally, with assembly and commissioning labour localised.

NoteRand-denominated EPC pricing is a genuine structural advantage

In most South African renewable financings the largest single procurement risk is the currency movement between budget approval and equipment payment, because modules, inverters and batteries are dollar- or yuan-priced. A rand-denominated fixed-price contract with the contractor carrying the hedging obligation transfers that exposure to the party best able to manage it, and removes a common source of pre-completion cost escalation. Due diligence should nonetheless confirm the contractor’s own hedging arrangements and its balance-sheet capacity to absorb the exposure, since a fixed price is only as good as the counterparty standing behind it, which is precisely what the parent company guarantee and performance security are for.