Sable Grid Storage Business Plan — Funding Requirement & Capital Structure

The Company is raising R615 million of equity, R465 million ordinary and R150 million mezzanine, alongside R1.435 billion of senior debt, to take Project…

Funding Requirement & Capital Structure

Jump to section

The Company is raising R615 million of equity, R465 million ordinary and R150 million mezzanine, alongside R1.435 billion of senior debt, to take Project Sizanani to financial close and commercial operations, with follow-on rights over the 350 MW pipeline.

16.1 Capital budget and sources

Figure 23. Project capital budget of R2.05 billion.

Instrument

Amount

Terms (indicative)

Senior debt

R1,435m

15-year door-to-door; ~11.5% all-in fixed via swap; 1.30× lock-up, 1.15× default DSCR; DFI-anchored syndicate

Ordinary equity

R465m

Sponsors and Mzansi Infrastructure Partners; drawn pro-rata with debt

Mezzanine / shareholder loans

R150m

Funds community trust participation; subordinated, repaid from distributions

Total sources

R2,050m

16.2 Stated versus effective gearing

Figure 24. Funding structure: stated versus effective gearing.
Key findingEffective gearing is 77:23, not 70:30

The Plan describes gearing of 70:30, calculated as senior debt against the R615 million described as equity. The R150 million mezzanine tranche within that figure is, however, subordinated debt: it carries a coupon, amortises on a defined schedule, is serviced ahead of shareholder distributions, and reduces distributable cash by approximately R32 million annually to year eight. Counting it where it economically belongs, total debt of R1,585 million against R465 million of true ordinary equity gives effective gearing of 77:23. This is not a criticism of the structure, mezzanine is a legitimate and common way to fund vendor-financed community participation, but it should be presented transparently, because senior lenders will assess total leverage and total debt service, not the sponsor’s classification, and because the difference between 70% and 77% leverage is material to how the credit is priced.

16.3 A consequence for the community trust

The Kganya Community Trust holds 15% of the Company on vendor-financed terms, repaid from distributions, and the mezzanine tranche funds that participation. The arithmetic consequence deserves explicit statement: because the mezzanine is serviced ahead of shareholder distributions and amortises to approximately year eight, the community trust receives limited distribution income until that debt is substantially repaid. Host communities will participate in profits, which is a genuinely better structure than construction employment alone, but they will do so from roughly year eight of operations, some ten years after the Company was incorporated. This is standard practice in South African renewable structures and is not a defect, but it should be communicated plainly to trustees and beneficiaries, and disclosed in the social performance reporting the Plan commits to.

16.4 Debt structure and covenants

Credit metric

Year 1

Year 3

Year 5

Year 10

Year 15

Senior debt outstanding (R million)

1395

1300

1183

749

0

Senior debt service (R million)

205

205

205

205

205

Mezzanine service (R million)

32

32

32

—

—

CFADS (R million)

321

356

381

391

503

DSCR, senior (×)

1.57×

1.74×

1.86×

1.91×

2.45×

DSCR, total debt (×)

1.35×

1.5×

1.61×

1.91×

2.45×

StrengthA conservative, well-structured debt package with genuine amortisation

Notwithstanding the definitional points above, the debt structure is sound. Fifteen-year fully amortising senior debt at a fixed all-in rate removes refinancing risk and interest-rate risk simultaneously, a materially more conservative structure than the mini-perm arrangements common in some markets. The 1.30× lock-up and 1.15× default covenants are standard for contracted infrastructure. A development-finance-anchored syndicate brings both patient capital and rigorous environmental and social diligence. And because the facility fully amortises within the contracted term, the project reaches the end of its capacity agreement debt-free, with a fully depreciated but operational asset and five years of remaining life, the source of the re-contracting upside excluded from the base-case returns.