Sable Grid Storage Business Plan — Implementation Roadmap
The programme runs from bid submission through financial close, an eighteen-month construction period, commercial operation and into the operating phase,…
Implementation Roadmap
Jump to section
- Overview & contents
- Important Notice & Confidentiality
- Executive Summary
- Company Overview & Governance
- Industry & Market Analysis
- Regulatory & Policy Environment
- Market Sizing & Demand Drivers
- Competitive Landscape & Positioning
- Products, Services & Revenue Model
- Project Sizanani, The Flagship Asset
- Technology & Engineering
- Grid Connection & Transmission Access
- Offtake Strategy & Counterparty Risk
- Construction, EPC & Procurement
- Operations, Maintenance & Asset Management
- Implementation Roadmap
- Financial Plan & Projections
- Funding Requirement & Capital Structure
- Returns, Scenarios & Sensitivity
- Risk Analysis & Independent Findings
- SWOT, PESTLE & Strategic Analysis
- Management Team & Organisation
- Transformation, Localisation & ESG
- Investor Returns, Exit & Conclusion
- Annexure A: Detailed Financial Statements
- Annexure B: Assumptions Book
- Annexure C: Scenario & Sensitivity Detail
- Annexure D: Development Pipeline
- Annexure E: Risk Register
- Annexure F: Glossary & Methodology
The programme runs from bid submission through financial close, an eighteen-month construction period, commercial operation and into the operating phase, with the first scheduled augmentation in year eight.
14.1 Phases and use of funds
|
Phase |
Timing |
Key milestones |
Funding deployed |
|---|---|---|---|
|
Bid & financial close |
M-6 to M0 |
Capacity agreement award; debt credit approval; swap execution; EPC and LTSA signature |
R45m development equity |
|
Early works |
M0–M3 |
Site establishment, access road, long-lead orders (transformers, 132 kV plant) |
R290m |
|
Main construction |
M3–M14 |
Civils, DC block delivery and installation, PCS and MV works |
R1,320m |
|
Grid & commissioning |
M12–M18 |
Connection energisation, cold and hot commissioning, capacity testing, COD |
R395m |
|
Operations ramp |
M18–M24 |
Availability optimisation, first distributions, Sizanani 2 bid preparation |
Operating cash flows |
14.2 Critical dependencies
|
Dependency |
Gates |
Mitigation |
|---|---|---|
|
Capacity agreement award |
Everything |
Parallel trader tolling route; staged development spend |
|
Site eligibility for the bid window |
Bid submission |
Confirm designated-site status in writing before bidding |
|
Self-build works agreement |
Financial close |
Conclude with network operator; fix scope and cost |
|
Senior debt credit approval |
Financial close |
DFI-anchored syndicate in advanced discussion |
|
Interest-rate swap execution |
Financial close |
Execute at close; sensitivity tested to +200bps |
|
EPC and LTSA signature |
Construction start |
Fixed-price wrap with parent guarantee and performance security |
|
Long-lead 132 kV plant |
Commissioning date |
Order in early works; supplier service levels |
The construction programme itself is credible, eighteen months from close to commercial operation is consistent with delivered four-hour storage projects of this scale, and battery installation is inherently faster and more modular than thermal or even solar construction. The uncertainty lies upstream and downstream of it. Upstream, the procurement programme has historically run behind schedule, and the interval between bid submission and award has been measured in quarters rather than weeks. Downstream, the delivery record is sobering: only about 9.2% of awarded storage capacity is operational, with roughly 45% awarded but not yet at commercial close. Investors should model a longer and less certain path to financial close than the six months the roadmap implies, and should ensure development capital is staged against milestones rather than committed in full at the outset.