Sable Grid Storage Business Plan — Implementation Roadmap

The programme runs from bid submission through financial close, an eighteen-month construction period, commercial operation and into the operating phase,…

Implementation Roadmap

Jump to section

The programme runs from bid submission through financial close, an eighteen-month construction period, commercial operation and into the operating phase, with the first scheduled augmentation in year eight.

Figure 14. Implementation roadmap from bid to commercial operation and beyond.

14.1 Phases and use of funds

Phase

Timing

Key milestones

Funding deployed

Bid & financial close

M-6 to M0

Capacity agreement award; debt credit approval; swap execution; EPC and LTSA signature

R45m development equity

Early works

M0–M3

Site establishment, access road, long-lead orders (transformers, 132 kV plant)

R290m

Main construction

M3–M14

Civils, DC block delivery and installation, PCS and MV works

R1,320m

Grid & commissioning

M12–M18

Connection energisation, cold and hot commissioning, capacity testing, COD

R395m

Operations ramp

M18–M24

Availability optimisation, first distributions, Sizanani 2 bid preparation

Operating cash flows

14.2 Critical dependencies

Dependency

Gates

Mitigation

Capacity agreement award

Everything

Parallel trader tolling route; staged development spend

Site eligibility for the bid window

Bid submission

Confirm designated-site status in writing before bidding

Self-build works agreement

Financial close

Conclude with network operator; fix scope and cost

Senior debt credit approval

Financial close

DFI-anchored syndicate in advanced discussion

Interest-rate swap execution

Financial close

Execute at close; sensitivity tested to +200bps

EPC and LTSA signature

Construction start

Fixed-price wrap with parent guarantee and performance security

Long-lead 132 kV plant

Commissioning date

Order in early works; supplier service levels

Analyst flagAn eighteen-month build is achievable; the programme timetable around it is less certain

The construction programme itself is credible, eighteen months from close to commercial operation is consistent with delivered four-hour storage projects of this scale, and battery installation is inherently faster and more modular than thermal or even solar construction. The uncertainty lies upstream and downstream of it. Upstream, the procurement programme has historically run behind schedule, and the interval between bid submission and award has been measured in quarters rather than weeks. Downstream, the delivery record is sobering: only about 9.2% of awarded storage capacity is operational, with roughly 45% awarded but not yet at commercial close. Investors should model a longer and less certain path to financial close than the six months the roadmap implies, and should ensure development capital is staged against milestones rather than committed in full at the outset.