Sable Grid Storage Business Plan — Investor Returns, Exit & Conclusion

The market has moved from promise to procurement. Storage is contracted through a repeatable government programme, the transmission build-out is funded,…

Investor Returns, Exit & Conclusion

Jump to section

22.1 Exit routes

  • Secondary sale to core infrastructure capital. De-risked, contracted storage assets trade at meaningful premiums to construction-stage equity once two years of operating history exist. This is the most common and most reliable route.
  • Platform consolidation. As the pipeline reaches 400 MW or more operational, the platform itself becomes an acquisition target for regional independent power producer aggregators, typically at a premium to the sum of the individual assets.
  • Refinancing distribution. Post-commissioning refinancing at operational risk pricing releases trapped equity without a sale, and is usually the earliest liquidity event available.

22.2 Why now

The market has moved from promise to procurement. Storage is contracted through a repeatable government programme, the transmission build-out is funded, the trading market is opening, and lenders have a precedent book. The scarce assets are exactly what the Company holds: grid connection in a constrained corridor, an empowered and experienced sponsor group, and a wrapped delivery structure. The window to enter at construction-stage returns, before the asset class reprices to operational infrastructure yields, is the current bid cycle.

22.3 Conclusion

Project Sizanani is a well-conceived asset in the right technology, in the right corridor, at the right point in South Africa’s energy transition, sponsored by a team with directly relevant delivery and financing experience and structured with unusual attention to risk transfer. The financial model reconciles arithmetically, the debt amortises fully within the contracted term at a fixed rate, and the technical assumptions carry deliberate headroom. Storage is also, uniquely among generation-adjacent assets, helped rather than hindered by the transmission congestion that constrains everything else in the Northern Cape.

The findings in this Plan do not contradict that assessment; they qualify it. The primary revenue route depends on a site-designated procurement programme whose structure the Company must confirm it fits. No contract has yet been awarded, and the tariff is a competitive outcome the Company cannot set. Debt-service cover, gearing and the equity return are each stated on a more favourable basis than a lender or a disciplined investor would apply. The maintenance reserve requires correction, and the tax treatment requires an opinion. These are resolvable, most of them before a single rand of construction capital is drawn, and resolving them is the work between this Plan and a financeable transaction.

R615m

Equity raise

17.6%

Construction-adjusted equity IRR

1.35×

Year-1 cover, strictest test

350 MW

Follow-on pipeline

StrengthThe request

Sable Grid Storage seeks R615 million of equity, R465 million ordinary and R150 million subordinated, alongside R1.435 billion of senior debt, to deliver Project Sizanani, a 100 MW / 400 MWh four-hour battery energy storage facility in the Northern Cape, with follow-on rights over a 350 MW pipeline. On the sponsor’s preserved figures the project delivers a construction-adjusted project return of approximately 14.5% and an equity return of approximately 17.6%, with senior debt-service cover averaging near 2.0x across the contracted term and full amortisation within it. Subject to confirmation of bid-window eligibility, award of the anchor capacity agreement, a written tax opinion and correction of the maintenance reserve, this is a credible, well-structured and financeable entry into an asset class that South Africa’s grid demonstrably needs.