Sable Grid Storage Business Plan — Products, Services & Revenue Model

Sable sells guaranteed, dispatchable capacity. Under the anchor capacity agreement the buyer receives the right to charge and discharge the facility within…

Products, Services & Revenue Model

Jump to section

Sable sells guaranteed, dispatchable capacity. Under the anchor capacity agreement the buyer receives the right to charge and discharge the facility within its operating envelope, and Sable is paid for tested availability rather than for energy throughput. This structure transfers utilisation and market risk to the offtaker and leaves the Company with the risks it can control: availability, round-trip efficiency and degradation management.

7.1 Revenue products

Product

Buyer

Contract form

Share of revenue

Capacity payments

National buyer / system operator

15-year availability-based capacity agreement

~91%

Ancillary services

System operator

Scheduled reserves and frequency regulation within the capacity envelope

~5%

Merchant arbitrage

Traders / market

Uncontracted envelope traded on peak/off-peak spreads

~4%

Figure 7. Revenue mix, contracted capacity dominates.

7.2 Unit economics

Metric

Base case

Basis

Capacity tariff

R300,000 / MW / month

Structured on recent storage procurement clearing levels; CPI-indexed

Contracted revenue, year 1

R360m

100 MW × tariff × 12 months at full availability

Ancillary + merchant, year 1

R36m

Scheduled reserves plus a conservative arbitrage allocation

Operating costs, year 1

R52m

LTSA, insurance, land, staffing, asset management, rates

EBITDA, year 1

R344m (86.9% margin)

Availability-based model carries minimal variable cost

Figure 8. Year-1 economics per megawatt of contracted capacity.

On a per-megawatt basis the economics are stark in their simplicity. Each megawatt of contracted capacity generates approximately R3.96 million of revenue against R0.52 million of operating cost, leaving R3.44 million of EBITDA. Depreciation absorbs roughly R1.03 million and interest a further R1.86 million, leaving a pre-tax margin of about R0.56 million per megawatt in the first year, rising steadily thereafter as inflation lifts the capacity payment while the debt service remains fixed in nominal terms. The business is, in the sponsor’s own phrase, availability infrastructure: capital-intensive, contract-anchored and operations-light.

7.3 Contracting philosophy

  • Contract first, build second. Construction begins only once the anchor capacity agreement and senior debt are executed, the discipline that separates infrastructure from speculation.
  • Match every revenue obligation with a wrapped supplier obligation. Availability guarantees in the capacity agreement are mirrored by availability liquidated damages in the long-term service agreement; capacity guarantees are mirrored by augmentation obligations.
  • Keep merchant exposure below 10% of revenue until the traded market deepens, revisited annually at board level within approved risk limits.

7.4 Follow-on products

Three adjacent products extend the model without changing its risk character. Firmed renewable products for licensed traders toll the storage capacity to shape solar and wind portfolios into round-the-clock supply blocks. Grid-deferral contracts with the transmission operator pay for postponing capital reinforcement in constrained corridors. And co-located storage for Northern Cape mining offtakers converts curtailed solar into firm, contracted supply under long-term tolling agreements. Each is a route to diversifying away from single-buyer dependence.

StrengthAvailability-based contracting is the right risk allocation for a first asset

The commercial architecture is well judged. By taking payment for availability rather than throughput, the Company avoids merchant price risk, dispatch risk and volume risk, the three exposures that have caused the most difficulty for storage investors in liberalised markets elsewhere. What remains is a set of engineering obligations that are measurable, insurable and contractually transferable to the technology partner. For a sponsor building its first asset, this is precisely the risk profile that should be sought, and it is the reason lenders will advance seventy percent gearing against a technology with barely a decade of utility-scale operating history.