Sable Grid Storage Business Plan — Project Sizanani, The Flagship Asset
Farm Zuurwater 62 (portion 3), near Aggeneys, Namakwa District, Northern Cape
Project Sizanani, The Flagship Asset
Jump to section
- Overview & contents
- Important Notice & Confidentiality
- Executive Summary
- Company Overview & Governance
- Industry & Market Analysis
- Regulatory & Policy Environment
- Market Sizing & Demand Drivers
- Competitive Landscape & Positioning
- Products, Services & Revenue Model
- Project Sizanani, The Flagship Asset
- Technology & Engineering
- Grid Connection & Transmission Access
- Offtake Strategy & Counterparty Risk
- Construction, EPC & Procurement
- Operations, Maintenance & Asset Management
- Implementation Roadmap
- Financial Plan & Projections
- Funding Requirement & Capital Structure
- Returns, Scenarios & Sensitivity
- Risk Analysis & Independent Findings
- SWOT, PESTLE & Strategic Analysis
- Management Team & Organisation
- Transformation, Localisation & ESG
- Investor Returns, Exit & Conclusion
- Annexure A: Detailed Financial Statements
- Annexure B: Assumptions Book
- Annexure C: Scenario & Sensitivity Detail
- Annexure D: Development Pipeline
- Annexure E: Risk Register
- Annexure F: Glossary & Methodology
8.1 Site and connection
|
Parameter |
Detail |
|---|---|
|
Location |
Farm Zuurwater 62 (portion 3), near Aggeneys, Namakwa District, Northern Cape |
|
Size / configuration |
100 MW / 400 MWh; four-hour duration; approximately 160 liquid-cooled LFP containers |
|
Grid connection |
132 kV loop-in to an existing transmission substation 4.2 km from site; budget quote secured; self-build works agreement in negotiation |
|
Land |
30-year notarial lease over 12 hectares with two 10-year renewals; servitude corridor registered |
|
Environmental status |
Basic assessment authorised; no fatal flaws; low-sensitivity brownfield-adjacent terrain |
|
Resource logic |
Corridor hosts heavy solar build-out with evening export constraint, the exact conditions that maximise storage value |
8.2 Delivery structure
The project will be delivered under a fixed-price, date-certain engineering, procurement and construction contract with VoltCore Technologies as integrator, wrapped by a parent company guarantee and 10% performance security. A twenty-year long-term service agreement includes capacity maintenance and scheduled augmentation in years eight and fourteen, holding usable energy at or above 95% of nameplate throughout the contracted term. Delay liquidated damages cover debt service during any construction overrun; performance liquidated damages buy down any capacity shortfall at commissioning.
The degradation and augmentation profile is central to the contracted proposition. At an average 2.2% annual capacity fade under a 330 equivalent-full-cycle regime, usable energy would fall below the 95% contracted floor within roughly three years absent intervention. The two scheduled augmentations restore capacity and are the mechanism by which the Company meets its fifteen-year obligation. Their funding is examined in Section 15, because the timing of that expenditure interacts directly with debt-service cover.
8.3 Development pipeline behind the flagship
|
Project |
Size |
Corridor |
Status |
|---|---|---|---|
|
Sizanani 2 |
150 MW / 600 MWh |
Northern Cape (Kenhardt corridor) |
Land secured; connection application lodged |
|
Umzansi Storage |
120 MW / 480 MWh |
Eastern Cape (wind corridor) |
Exclusivity over site; feasibility underway |
|
Highveld Flex |
80 MW / 320 MWh |
Mpumalanga (coal-retirement node) |
Pre-feasibility; grid study commissioned |
The pipeline gives investors follow-on deployment at declining development cost per megawatt, with shared corporate overhead and repeatable contracting. It is also strategically well diversified: a second Northern Cape asset in a solar corridor, an Eastern Cape asset in a wind corridor with a different generation profile, and a Mpumalanga asset at a coal-retirement node where flexibility will be needed as thermal plant withdraws. Investors should nonetheless note that pipeline value is contingent on the flagship reaching close and performing; it is optionality, not an asset.