Sable Grid Storage Business Plan — Project Sizanani, The Flagship Asset

Farm Zuurwater 62 (portion 3), near Aggeneys, Namakwa District, Northern Cape

Project Sizanani, The Flagship Asset

Jump to section

8.1 Site and connection

Parameter

Detail

Location

Farm Zuurwater 62 (portion 3), near Aggeneys, Namakwa District, Northern Cape

Size / configuration

100 MW / 400 MWh; four-hour duration; approximately 160 liquid-cooled LFP containers

Grid connection

132 kV loop-in to an existing transmission substation 4.2 km from site; budget quote secured; self-build works agreement in negotiation

Land

30-year notarial lease over 12 hectares with two 10-year renewals; servitude corridor registered

Environmental status

Basic assessment authorised; no fatal flaws; low-sensitivity brownfield-adjacent terrain

Resource logic

Corridor hosts heavy solar build-out with evening export constraint, the exact conditions that maximise storage value

8.2 Delivery structure

The project will be delivered under a fixed-price, date-certain engineering, procurement and construction contract with VoltCore Technologies as integrator, wrapped by a parent company guarantee and 10% performance security. A twenty-year long-term service agreement includes capacity maintenance and scheduled augmentation in years eight and fourteen, holding usable energy at or above 95% of nameplate throughout the contracted term. Delay liquidated damages cover debt service during any construction overrun; performance liquidated damages buy down any capacity shortfall at commissioning.

Figure 9. Usable capacity, degradation and scheduled augmentation.

The degradation and augmentation profile is central to the contracted proposition. At an average 2.2% annual capacity fade under a 330 equivalent-full-cycle regime, usable energy would fall below the 95% contracted floor within roughly three years absent intervention. The two scheduled augmentations restore capacity and are the mechanism by which the Company meets its fifteen-year obligation. Their funding is examined in Section 15, because the timing of that expenditure interacts directly with debt-service cover.

8.3 Development pipeline behind the flagship

Figure 10. Development platform: flagship plus 350 MW pipeline.

Project

Size

Corridor

Status

Sizanani 2

150 MW / 600 MWh

Northern Cape (Kenhardt corridor)

Land secured; connection application lodged

Umzansi Storage

120 MW / 480 MWh

Eastern Cape (wind corridor)

Exclusivity over site; feasibility underway

Highveld Flex

80 MW / 320 MWh

Mpumalanga (coal-retirement node)

Pre-feasibility; grid study commissioned

The pipeline gives investors follow-on deployment at declining development cost per megawatt, with shared corporate overhead and repeatable contracting. It is also strategically well diversified: a second Northern Cape asset in a solar corridor, an Eastern Cape asset in a wind corridor with a different generation profile, and a Mpumalanga asset at a coal-retirement node where flexibility will be needed as thermal plant withdraws. Investors should nonetheless note that pipeline value is contingent on the flagship reaching close and performing; it is optionality, not an asset.