Sable Grid Storage Business Plan — Risk Analysis & Independent Findings

Confirm designated-site status in writing; elevate trader tolling route

Risk Analysis & Independent Findings

Jump to section

18.1 Risk matrix

Risk

Likelihood

Impact

Mitigation

Site not eligible for a designated bid window

Medium

Critical

Confirm designated-site status in writing; elevate trader tolling route

Procurement timing slips

High

High

Parallel trader tolling; development spend staged against milestones

Clearing tariff below assumption

Medium-High

High

Board-approved bid floor; disciplined walk-away

Construction delay or cost overrun

Medium

High

Fixed-price EPC with delay LDs sized to debt service; 8% contingency

Battery performance / degradation

Low

High

LTSA capacity guarantees with augmentation; availability LDs

Grid connection delay

Medium

Medium

Self-build works agreement; early long-lead procurement; budget quote secured

Accelerated tax allowance unavailable

Medium

Medium

Written tax opinion before close; model the unrelieved case

Maintenance reserve under-funded

Medium

Medium

Increase years 9–13 funding rate; forward-looking reserve test

Interest rate movement pre-close

Medium

Medium

Swap executed at financial close; tested to +200bps

FX on imported equipment

Low-Medium

Medium

ZAR-denominated EPC with supplier hedging

Offtaker credit

Low

High

Government support framework; trader route diversifies over time

Single-asset concentration

High

Medium

Pipeline execution; portfolio diversification over time

Social licence / community disruption

Low

Medium

15% community equity, local employment, grievance mechanism

Cyber & physical security

Medium

Medium

IEC 62443 controls, segmented networks, 24/7 monitoring, BI insurance

18.2 Independent findings

Key finding, The primary revenue route depends on a site-designated programme

All three storage bid windows to date have designated the substations at which projects may be built, appointing a single preferred bidder per site, most recently in the Free State supply area with a contracted capacity band of 123 to 124 MW. A developer-originated 100 MW facility at Aggeneys does not obviously qualify unless that substation is designated. Approximately 91% of base-case revenue depends on resolving this. It should be confirmed in writing before further development capital is committed.

Key finding, There is no contracted revenue; this is development-stage risk

The Company is bid-ready, not awarded. Roughly R45 million of development equity is at risk before any contract exists, and the entire capital structure is conditional on award. Investors entering at this stage take procurement risk, which is qualitatively different from the contracted infrastructure risk the Plan otherwise describes and should be priced accordingly.

Key finding, Debt-service cover is 1.35× on the strictest test, not 1.68×

The stated 1.68× is EBITDA-based. On cash flow after tax and reserve funding, senior cover is 1.57×; including mezzanine service ranking ahead of distributions, cover is 1.35× against a 1.30× lock-up. Cover strengthens materially thereafter, but Year 1 is tight and lenders will covenant against the stricter measure.

Key finding, Effective gearing is 77:23

The R150 million mezzanine is subordinated debt counted within the stated equity. Total debt of R1,585 million against R465 million of ordinary equity gives 77% leverage, not 70%.

Key finding, The maintenance reserve appears roughly R95 million short of the year-14 augmentation

Funding of approximately R68 million across years nine to thirteen faces a R150 million obligation. The funding rate should approximately double, or the shortfall will compress the year-fourteen distribution.

Key finding, Accelerated capital allowances may not extend to standalone storage

The relief applies to plant used in generating electricity from renewable sources; a standalone battery stores rather than generates. Without it, cumulative cash tax across the first five years rises by roughly R140 million and minimum senior cover falls from 1.57× to 1.49×. A written tax opinion should be a condition precedent.

Key finding, The equity IRR is stated on a different basis from the project IRR

The project IRR reconciles precisely on a construction-adjusted basis. The equity IRR appears to be measured from commercial operation. Restated consistently, the equity return is approximately 17.6% rather than 19.8%.

Strength, Against these findings, the structure and the sponsor are genuinely strong

The model reconciles arithmetically, the debt fully amortises within the contracted term at a fixed rate, the technical assumptions carry deliberate headroom, the engineering contract is rand-denominated with the contractor carrying currency risk, the revenue structure transfers market and utilisation risk to the offtaker, the empowerment architecture is substantive rather than cosmetic, and the executive team has directly relevant delivery and financing experience. Storage is also the rare asset class whose grid access is helped rather than hindered by corridor congestion. Corrected for the findings above, this is a well-conceived and financeable proposition.

  • Written confirmation that the Aggeneys site is eligible for the bid window the Company intends to enter, or a documented decision to pursue trader tolling as the primary route.
  • Award of the capacity agreement, or an executed tolling agreement of comparable tenor and credit quality, before drawdown of construction capital.
  • A board-approved minimum bid tariff below which the Company will not bid, evidenced to investors.
  • Concluded self-build works agreement and evidence of an accepted and paid connection budget quote.
  • Written tax opinion on the availability of accelerated capital allowances to standalone storage.
  • Revised maintenance reserve schedule fully funding both augmentations on a forward-looking basis.
  • Restated returns and coverage presentation on a consistent basis: CFADS-based cover including all senior-ranking debt service, and construction-adjusted returns.
  • Executed fixed-price EPC and 20-year LTSA with parent company guarantee and performance security.