MEGAPOWER Solar — Strategy, Sales & Marketing

The strategic pillars, the two commercial pathways — REIPPPP Bid Window 8 and corporate / wheeled PPA — the PPA term sheet, stakeholder and regulatory engagement, and ESG positioning.

MEGAPOWER Solar Business PlanSection 6 › Strategy, Sales & Marketing

Section 6 · Business Plan

Strategy, Sales & Marketing

The strategic pillars, the two commercial pathways — REIPPPP Bid Window 8 and corporate / wheeled PPA — the PPA term sheet, stakeholder and regulatory engagement, and ESG positioning.

In a B2B, contract-driven market like utility-scale solar IPPs,
“sales and marketing” translates into a focused, multi-quarter campaign
of regulatory engagement, contracting and stakeholder positioning. This
section sets out MEGAPOWER’s strategic posture, our two-pathway
commercial strategy and our ESG positioning.

6.1 Strategic Pillars

  • Build the project to a debt-fundable threshold by
    Q1-2027.
    Every workstream is sequenced to clear lender
    due-diligence requirements before financial close — secured land, EIA
    approval, NERSA generation licence, EPC term sheet, signed PPA,
    completed independent yield study, and credit-rated insurance and
    counterparty support.
  • Optimise for execution risk over headline
    tariff.
    We will not chase the absolute lowest tariff at the
    expense of construction and operating margins. Our bid will price
    contingency for module FX exposure, reasonable EPC margin and a
    sustainable O&M reserve.
  • Hold dual contracting pathways. We will
    simultaneously prepare a REIPPPP submission and pre-negotiate a
    portfolio of corporate / wheeled PPAs. The dual track gives us
    optionality to execute on whichever channel reaches contractual finality
    first.
  • Deliver verifiable B-BBEE outcomes. Our 20%
    community-trust ownership and audited social-investment programme are
    designed for top-quartile economic-development scoring, not as
    compliance artefacts.
  • Compound to a portfolio. Profitable, on-time
    delivery of the first 100 MW project becomes the credibility platform
    for the second 100-200 MW project, en route to 1 GW of contracted
    capacity by 2032.

6.2 Commercial Strategy: Two Pathways

6.2.1 Pathway A — REIPPPP Bid Window 8

Bid Window 8 is targeted by the IPP Office for procurement of
approximately 3 GW, with a mandatory 4-hour battery-storage requirement
on 40% of awarded capacity. MEGAPOWER will submit in the unconstrained
PV category (i.e., without storage) for the project’s full 100 MW.
Submission economics are summarised below:

Item Value Notes
Tariff bid (real, 2026 ZAR) ZAR 0.50 / kWh Mid-range vs. BW7 cleared at 0.47
Tariff escalation CPI Standard REIPPPP indexation
PPA tenor 20 years Standard
Financial close deadline 12 months from preferred-bidder Standard REIPPPP
Local-content target ≥ 45% Above BW7 minimum
Economic-development score Top-quartile 20% B-BBEE Trust
Bid security ZAR 100,000 / MW Standard, returnable

6.2.2 Pathway B — Corporate / Wheeled PPA

In parallel, MEGAPOWER will pursue corporate offtake under a
portfolio of wheeled PPAs aggregated to 100 MW capacity. The targeted
offtaker pool is structured to ensure no single offtaker accounts for
more than 35% of project revenue:

Offtaker Type Target Capacity Tariff Range Tenor
Mining major (anchor) 30-40 MW ZAR 0.95-1.05 / kWh 15 years
Heavy-industrial offtaker 20-25 MW ZAR 0.95-1.10 / kWh 12-15 years
Hyperscale data-centre 20-30 MW ZAR 0.85-1.00 / kWh 12-15 years
Manufacturing aggregator 10-20 MW ZAR 0.95-1.05 / kWh 10-12 years
Utility-grade balance / merchant 5-10 MW Spot / time-of-use Day-ahead
Total contracted 100 MW Blended ~0.95 Weighted ~14 years

Pathway B has higher headline tariff economics but introduces
structural counterparty diversification risk and additional contracting
cost. MEGAPOWER’s analysis (see Section 9) shows that both pathways are
bankable under base-case assumptions, with the corporate-PPA pathway
producing approximately 2.3 percentage points of additional levered IRR
but a ~0.20x lower minimum DSCR.

6.3 PPA Term Sheet

Whether under REIPPPP or corporate contracting, MEGAPOWER’s PPA term
sheet will be anchored on the following principal commercial terms:

Term Provision
Tenor 20 years (REIPPPP) / 12-15 years (corporate)
Tariff escalation CPI (REIPPPP) or 6-7% fixed (corporate)
Take-or-pay Yes — minimum take 90% of contracted volume
Curtailment Compensated above 1.0% annual cap
Performance guarantee Plant-level availability guarantee with LDs
Currency ZAR (with optional USD-linked tranche for hyperscale)
Force majeure Standard PPA F.M. carve-outs incl. grid unavailability
Termination Tail value protected by step-in rights for lenders
Change-in-law Tariff adjustment for material adverse change

6.4 Stakeholder & Regulatory Engagement

Successful execution requires sustained engagement with five distinct
stakeholder groups. Engagement plans, named owners and KPIs are tracked
in our internal Stakeholder Management Plan.

Stakeholder Objective Engagement Cadence
IPP Office (DMRE) Track BW8 tender release; maintain pipeline visibility Monthly briefings + bid submissions
NERSA Generation licence; tariff approval where applicable Quarterly + as-required
Eskom Grid Access Unit Maintain budget quote validity; coordinate connection works Bi-monthly
Provincial / local government Land-use authorisations; community engagement Quarterly + as required
Host community (Trust beneficiaries) Quarterly liaison forum; programme delivery accountability Quarterly forum + monthly site presence
DFI / commercial lenders Quarterly project updates; monthly during construction Quarterly Steering Committee

6.5 ESG & Sustainability Positioning

ESG is no longer a stewardship overlay — it is a primary determinant
of cost-of-capital and offtaker eligibility. MEGAPOWER’s ESG positioning
is anchored on third-party verifiable outcomes.

Pillar Metric Target
Environmental — emissions avoided tCO₂e / year avoided vs. SA grid factor ~210,000 tCO₂e / year
Environmental — water ML / GWh consumed for cleaning < 0.10 ML / GWh
Environmental — biodiversity Critical Biodiversity Areas affected Zero (CBA exclusion at site selection)
Social — local employment Construction + operations FTEs (50 km radius) ≥ 350 construction; ≥ 25 operations
Social — community spend % of project revenue to Trust programmes 1.5% Y1 → 3.0% Y10
Governance Independent NEDs / total board ≥ 30%
Governance — reporting External ESG audit + annual GRI report Year-1 onwards

The project is designed to qualify for green-bond / climate-finance
sources (Green Climate Fund, AfDB SEFA, IFC) which can deliver
concessional pricing and longer tenors than traditional commercial debt.
We have provisionally targeted ZAR 92.5 m of mezzanine / concessional
debt under this category.

Confidential — this business plan is provided to prospective investors and lenders for evaluation purposes only and may not be reproduced or distributed without the written consent of MEGAPOWER Solar Power (Pty) Ltd.