PurePastures Dairy Business Plan — Implementation Roadmap

Section 11 · 12 of 16

Implementation Roadmap

The plan is sequenced across four years and nine workstreams, front-loading the automation, cold-chain and solar investments that underpin margin, then layering product launches, national retail expansion, phase-2 regional nodes and SADC export. Critical milestones and dependencies are shown in the Gantt chart below.

Figure 11.1 Four-year implementation roadmap and critical milestones

11.1 Phasing logic and dependencies

  • Foundation (FY2026): Close funding, fund the DSRA, and begin automation procurement and cold-chain upgrades. Re-certify HACCP/ISO 22000. Launch lactose-free and high-protein lines. Solar design and EPC procurement commence.
  • Build-out (FY2026–27): Automation install and commissioning at the Gauteng hub; solar installation and grid-tie; traceability platform goes live; national retail listings and premium brand campaign; Botswana and Namibia export entry.
  • Scale (FY2027–28): Cape Town packaging/distribution node; artisanal cheese launch; Zambia and Mozambique export ramp; AI route-optimisation fully deployed.
  • Consolidation (FY2028–29): Durban node build-out; functional/probiotic range launch; de-gearing and dividend initiation as the business reaches net-cash.

NoteCritical path

The automation commissioning and yield ramp (H2 FY2027) is the single most important dependency, it underpins the modelled margin expansion and the cash generation that funds phase-2 nodes and export. Slippage here would push out both the margin curve and the self-funding transition, which is why it is prioritised immediately after funding close.

11.2 Key milestones

Milestone

Target

Significance

Funding close & CP satisfaction

Q1 FY2026

Unlocks the full programme

Automation commissioning & ramp

H2 FY2027

Drives margin expansion

Solar grid-tie live

FY2027

Cost & ESG step-change

Traceability platform live

FY2027

Premium & export enabler

Cape Town node operational

FY2028

Freshness, cost, export reach

Net-cash position reached

FY2029

De-risks the credit

Durban node & functional range

FY2029

Completes the platform

Table 11.1 Critical milestones and their significance.