SafeRide Insurance Solutions — Implementation Plan & Gantt Chart

The following implementation plan outlines the key activities, milestones, and timelines for SafeRide’s establishment and launch over an 18-month pre-launch and initial operating period. The Gantt chart below provides a visual representation of the parallel and sequential work streams required to achieve…

SafeRide Insurance Solutions (Pty) Ltd Business Plan › Implementation Plan & Gantt Chart

Section 14 · Business Plan

Implementation Plan & Gantt Chart

The following implementation plan outlines the key activities, milestones, and timelines for SafeRide’s establishment and launch over an 18-month pre-launch and initial operating period. The Gantt chart below provides a visual representation of the parallel and sequential work streams required to achieve…

14.1 Implementation Overview

The following implementation plan outlines the key activities, milestones, and timelines for SafeRide’s establishment and launch over an 18-month pre-launch and initial operating period. The Gantt chart below provides a visual representation of the parallel and sequential work streams required to achieve commercial launch.

14.2 Key Milestones

Milestone Target Date Dependencies
Company Registration (CIPC) Month 1 Founders’ agreement signed
Seed Capital Secured Month 3 Investor commitments
FSCA Licence Application Submitted Month 2 Company registered, compliance plan
Technology Platform MVP Complete Month 6 Development team recruited
FSCA Licence Granted Month 5–6 Application approved
Reinsurance Treaty Signed Month 6 Licence obtained, actuarial pricing
Staff Recruitment Complete (Phase 1) Month 7 Office operational
Marketing Campaign Launch Month 7 Brand identity finalised
Pilot Launch (Gauteng, 500 policies) Month 8–9 All systems operational
Full Commercial Launch Month 10 Pilot review positive
Fleet Insurance Product Launch Month 11–12 Fleet underwriting guidelines
KZN & WC Expansion Month 13–15 Gauteng operations stable
Series A / Growth Capital Raise Month 16–18 Year 1 financial results

14.3 Implementation Gantt Chart

The Gantt chart below illustrates the parallel execution of key work streams over the 18-month implementation period. Coloured bars indicate the duration of each activity:

Activity M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18
Company Registration & Licensing
FSCA Regulatory Approval
Capital Raising & Investor Engagement
Technology Platform Development
Office Setup & Infrastructure
Staff Recruitment & Training
Reinsurance Treaty Placement
Marketing & Brand Launch
Pilot Launch (Gauteng)
Full Commercial Launch
KZN & Western Cape Expansion
Fleet Insurance Product Launch
Digital-Only Policies Nationwide
Performance Review & Series B Planning

14.4 Critical Path

The critical path runs through FSCA regulatory approval (Months 2–6), which is the primary gating item for commercial launch. Technology platform development runs in parallel, with the MVP targeted for completion by Month 6 to align with the expected licence approval timeline. Any delay in FSCA approval will delay the pilot and commercial launch dates proportionally. The management team will mitigate this risk through early and proactive engagement with the regulator.