Kenya Greenmaster Fresh Business Plan — Implementation Roadmap

The phases from first 45 hectares to 370, packhouse and certification build, dependencies and the gate at each stage.

Implementation Roadmap

Jump to section
On this page

  • 13.1 Development programme
  • 13.2 Critical dependencies
  • 13.3 Conditions precedent to drawdown
Implementation roadmap — the retail programmes gate the prepared capital
Figure 23. Implementation roadmap — the retail programmes gate the prepared capital.

13.1 Development programme

Phase

Months

Activities

Gate — do not proceed without

1. Conditions precedent

1 to 6

Secure European retail programme indications covering a majority of planned first-year prepared volume; appoint the technical director and head of prepared operations; contract first-year hectarage and map collection catchments; obtain a credit-approved receivables facility and term loan

All seven conditions precedent satisfied. Equity drawdown follows, not precedes

2. Build and certify

6 to 16

Packhouse fit-out and cold chain commissioning; collection centres and field cold rooms across two counties; group certification with internal control system and first audits; systems approach for regulated pests established with the inspectorate

Group certification granted; first bulk consignment shipped

3. Bulk then prepared

16 to 31

Bulk export at 45 hectares while measuring pack-out and grading discipline; build the prepared and high-care facility; retail food safety standard audit and certification

High-care facility certified; first prepared revenue. Capture above 30% by end FY2028 or stop expanding

4. Scale the base

Years 3 to 4

Commission the avocado grading and packing line; scale to 200 hectares and prepared capture to 48%

Capture holding at plan; facility headroom above US$0.50m

5. Reach maturity

Years 4 to 5

Second facility provider; scale to 370 hectares and 1 600 growers with capture at 60%

81% of field weight reaching Europe

13.2 Critical dependencies

Dependency

What it gates

Why it cannot be accelerated

Retail programme indications

The prepared capital commitment

European category buyers plan seasonally. The conversation cannot be compressed and the facility has no alternative use

Technical director appointment

Certification and the systems approach

The licence to trade depends on it, and the certification body engages with a named responsible person

Group certification

Any European sale

Requires an internal control system, documented audits of every grower, and traceability from pack to plot

Systems approach for regulated pests

Sustained market access

Documented pest management from plot to pack. Established before the first consignment, not after the first interception

Collection centres and field cold rooms

Shelf life at the European end

Field heat removal within two hours. Distributed infrastructure across two counties takes a full build season

Retail food safety standard

First prepared revenue

Audits a facility in operation. Certification cannot precede commissioning

Credit-approved receivables facility

The trade cycle from FY2028

Equity should not fund a trade cycle a facility was assumed to carry

Three seasons of grower delivery history

Reliable supply and lower side-selling

Cannot be bought. It is the accumulated result of paying reliably and buying the whole harvest

13.3 Conditions precedent to drawdown