Highveld Detailing Business Plan — Appendix B: Roll-out Schedule

The site-by-site roll-out schedule underpinning the volume and capital build.

Section 37 of 38

Appendix B: Roll-out Schedule

Jump to section

Table 70. Unit mobilisation and closure schedule by month

Channel

Mobilisation months from funding close

Detailing studios

Midrand (flagship): opens month 3; Centurion: opens month 22

In-dealership units

7, 10 (contract lost at 31), 14, 16, 18, 20 (contract lost at 43), 22, 24, 26, 28, 29, 31, 32, 34 (contract lost at 55), 35, 36, 38, 39, 41, 42, 44, 45, 47, 48, 50, 51, 53, 54, 56, 57, 59

Mobile fleet units

5, 6, 19, 20, 33, 34

Modelled contract losses

Months 31, 43 and 55 — one embedded unit lost on each occasion, reflecting a realistic contract non-renewal rate

Table 71. Operating units at each year end

FY2028

FY2029

FY2030

FY2031

FY2032

Detailing studios

1

2

2

2

2

In-dealership units

2

8

15

22

28

Mobile fleet units

2

4

6

6

6

Total operating units

5

14

23

30

36

Vehicles processed

8 871

39 594

83 849

131 614

172 876

Closing headcount

33

88

139

183

223