Vellore Pizza Co. — Implementation Roadmap

The phased implementation roadmap, with key milestones from launch and store build-out through the franchise rollout to network scale-up.

Vellore Pizza Co. Business PlanSection 10 › Implementation Roadmap

Section 10 · Business Plan

Implementation Roadmap

The phased implementation roadmap, with key milestones from launch and store build-out through the franchise rollout to network scale-up.

The Company’s implementation plan spans a 24-month horizon from
financial close, organised into three sequential but overlapping phases:
Phase 0 (Foundation), Phase 1 (Launch) and Phase 2
(Scale).
The roadmap is structured to de-risk the build
sequentially — establishing supply, technology and the initial corporate
estate before opening the franchise channel — while running parallel
workstreams to compress time-to-scale.

10.1 Phased Approach

Phase 0 — Foundation (Months 1–6)

  • Close capital raise; finalise legal structure and
    governance.
  • Recruit executive and operations leadership.
  • Negotiate supplier and cheese supply agreements at network
    scale.
  • Commence central commissary site acquisition and build; begin
    technology platform development.
  • Select and begin fit-out of first flagship sites.

Phase 1 — Launch (Months 7–12)

  • Open flagship corporate stores 1–3; launch brand and
    marketing.
  • Commission commissary; bring first stores onto central
    supply.
  • Complete and beta-test ordering app; integrate delivery.
  • Finalise franchise model and legal documentation.
  • Begin rollout of corporate stores 4–8.

Phase 2 — Scale (Months 13–24)

  • Launch first franchise recruitment drive; onboard franchise
    stores 1–6.
  • Roll out loyalty programme and data platform.
  • Complete corporate estate to plan; commence Phase 2 city
    expansion planning (Durban, Cape Town and beyond).

10.2 Gantt Chart — Critical Path, Milestones & Dependencies

The Gantt chart below sets out the implementation timeline by
workstream, showing task durations, milestones and the critical
dependencies that govern the sequencing. The critical
path
runs through the commissary build and the technology
platform: store openings and franchise onboarding are gated by the
availability of central supply and the ordering system, which is why
both are initiated in Phase 0 and prioritised for capital and management
attention.

Figure 10.1
Figure 10.1 — 24-month implementation roadmap (Gantt). Bars show task duration by month from financial close; colours denote workstream.

10.3 Key Milestones & Dependencies

Milestone Target Critical dependency
Financial close Month 1 Equity + debt commitments executed
Commissary operational Month 12 Site, build, equipment commissioning
First 3 flagships trading Month 11 Sites, fit-out, supply, staff
Ordering app live Month 13 Development, delivery integration, beta
Franchise model launched Month 13 Legal docs, operating manuals
First franchise stores open Month 16 Recruitment, onboarding, supply capacity
8 corporate stores trading Month 18 Capital, sites, commissary capacity
Phase 2 expansion planned Month 24 FY1 performance validation

Confidential — this business plan is provided to prospective investors and lenders for evaluation purposes only and may not be reproduced or distributed without the written consent of Vellore Pizza Co. (Pty) Ltd.