Aurora Downstream Energy — Implementation Roadmap

The phasing overview and the work packages, dependencies and milestones from financial close through the phased build and ramp.

Aurora Downstream Energy Business PlanSection 10 › Implementation Roadmap

Section 10 · Business Plan

Implementation Roadmap

The phasing overview and the work packages, dependencies and milestones from financial close through the phased build and ramp.

Aurora Energy’s build-out is sequenced over a 60-month horizon from
financial close, organised into five workstreams — funding &
licensing, infrastructure, commercial, operations & systems, and
expansion — with clearly defined milestones and dependencies. The
roadmap is deliberately conservative on licensing and commissioning
lead-times, recognising these as the principal execution risks.

Figure 7
Figure 7. 60-month implementation roadmap and critical-path Gantt across five workstreams, with key milestones marked.

10.1 Phasing overview

Table 14. Implementation phases and
objectives

Phase Period Objective Key outcomes
Phase 1 — Establish Months 0–12 Close funding, secure licences & terminal access, build core platform Financial close, licences lodged, JHB depot & bottling, fleet, first deliveries
Phase 2 — Ramp Months 12–24 Commission and ramp to steady-state utilisation Anchor contracts live, network rollout, EBITDA break-even trajectory
Phase 3 — Expand Months 24–36 Coastal depots and rural network expansion National footprint, diversified volumes
Phase 4 — Diversify Months 36–60 Value-added services and regional assessment Bunkering pilot, SADC entry assessment, exit-readiness

10.2 Work packages, dependencies & milestones

Table 15. Critical-path work packages and
dependencies

Work package Start Duration Depends on Milestone
Financial close & equity drawdown M0 3m Investment decision M3: Financial close
Petroleum & LPG licensing M1 6m Financial close Licences granted
Terminal throughput agreements M2 4m Financial close Supply secured
JHB depot & bottling build M4 10m Licensing, terminal access Plant commissioned
Fleet & cylinder pool M5 9m Financial close Fleet operational
ERP & systems go-live M6 8m Funding Systems live
Anchor industrial contracts M6 9m Brand, supply security Base-load secured
Commissioning & first deliveries M12 4m Plant, fleet, supply M12: First deliveries
Ramp to steady state M16 14m Commissioning M24: Break-even trajectory
Coastal & rural expansion M24 14m Steady-state ops M36: National footprint
Bunkering & SADC assessment M42 12m+ National platform M54: Phase-3 / regional
Analyst note — schedule risk The critical path runs through financial close → licensing and
terminal access → plant commissioning → first deliveries (targeted at
Month 12). Slippage in licensing or terminal-access agreements is the
most material schedule risk and would push out the revenue ramp; the
debt structure’s 24-month repayment grace period and funded debt-service
reserve are sized to absorb reasonable commissioning delays.

Confidential — this business plan is provided to prospective investors and lenders for evaluation purposes only and may not be reproduced or distributed without the written consent of Aurora Downstream Energy (Pty) Ltd.