GoldenNest Poultry Farms — Implementation Timeline
The following table presents the projected implementation schedule from funding approval to full-capacity production:
Section 15 · Business Plan
Implementation Timeline
The following table presents the projected implementation schedule from funding approval to full-capacity production:
The following table presents the projected implementation schedule from funding approval to full-capacity production:
| Milestone | Target Date | Duration |
| Funding Approval and Drawdown | Month 0 | – |
| Company Registration and Licensing | Month 0–1 | 4 weeks |
| Land Acquisition and Transfer | Month 1–2 | 8 weeks |
| Environmental Impact Assessment | Month 1–4 | 12 weeks |
| Farm Design and Planning Approvals | Month 2–4 | 8 weeks |
| Construction: Site Preparation and Civil Works | Month 3–6 | 12 weeks |
| Construction: Poultry Houses and Equipment Installation | Month 4–8 | 16 weeks |
| Procurement: Layer Hens (Point-of-Lay Pullets) | Month 7–8 | 4 weeks |
| Staff Recruitment and Training | Month 6–8 | 8 weeks |
| Commissioning and Test Production | Month 8–9 | 4 weeks |
| First Commercial Egg Production | Month 9–10 | – |
| Full Production Capacity (100,000 Birds) | Month 12 | – |