GoldenNest Poultry Farms — Implementation Timeline

The following table presents the projected implementation schedule from funding approval to full-capacity production:

GoldenNest Poultry Farms (Pty) Ltd Business Plan › Implementation Timeline

Section 15 · Business Plan

Implementation Timeline

The following table presents the projected implementation schedule from funding approval to full-capacity production:

The following table presents the projected implementation schedule from funding approval to full-capacity production:

Milestone Target Date Duration
Funding Approval and Drawdown Month 0
Company Registration and Licensing Month 0–1 4 weeks
Land Acquisition and Transfer Month 1–2 8 weeks
Environmental Impact Assessment Month 1–4 12 weeks
Farm Design and Planning Approvals Month 2–4 8 weeks
Construction: Site Preparation and Civil Works Month 3–6 12 weeks
Construction: Poultry Houses and Equipment Installation Month 4–8 16 weeks
Procurement: Layer Hens (Point-of-Lay Pullets) Month 7–8 4 weeks
Staff Recruitment and Training Month 6–8 8 weeks
Commissioning and Test Production Month 8–9 4 weeks
First Commercial Egg Production Month 9–10
Full Production Capacity (100,000 Birds) Month 12