GreenScape Landscapes Business Plan — Implementation Roadmap

The phases from first contracts to full crew complement, dependencies and the gate at each stage.

Section 18 of 25

Implementation Roadmap

Jump to section

A phased 36-month plan establishes recurring revenue before pursuing commercial and geographic expansion — capital and management attention follow proof, not ambition.

The roadmap sequences the build across five phases over 36 months, from setup and launch through ramp-up, scale-up and expansion. Recurring revenue and route density are established first; commercial contracts, project scale-up and geographic expansion follow the proven base.

36-month implementation roadmap and critical path across setup, launch, ramp-up, scale-up and expansion
Figure 1. 36-month implementation roadmap and critical path across setup, launch, ramp-up, scale-up and expansion.

Table 32. Implementation phases, milestones and deliverables

Phase

Timing

Key activities & milestones

1. Setup

Months 1–2

Incorporate; secure premises; procure equipment & fleet; develop brand & website; establish suppliers; recruit initial three teams.

2. Launch

Months 2–4

Launch digital marketing; acquire residential customers; establish maintenance routes; start referral programme; begin first projects.

3. Commercial development

Months 4–9

Approach estates & property managers; bid for commercial contracts; expand teams; develop irrigation division.

4. Scale-up

Months 9–18

Grow recurring contracts; add vehicles & teams (4–7); second depot; increase project capacity; broaden coverage.

5. Expansion

Years 2–5

Scale to 13 teams; target national property managers; expand commercial contracts; grow water-wise division; enter Pretoria/Centurion/Midrand; evaluate branch model.