Karoo Harvest Produce — Implementation Plan & Gantt Chart

The project will be implemented over a 24-month period divided into two principal phases. Phase 1 (Months 0–12) encompasses all development activities including land acquisition, infrastructure construction, equipment procurement, and trial planting. Phase 2 (Months 12–24) transitions to full commercial operations, first…

Karoo Harvest Produce (Pty) Ltd Business Plan › Implementation Plan & Gantt Chart

Section 11 · Business Plan

Implementation Plan & Gantt Chart

The project will be implemented over a 24-month period divided into two principal phases. Phase 1 (Months 0–12) encompasses all development activities including land acquisition, infrastructure construction, equipment procurement, and trial planting. Phase 2 (Months 12–24) transitions to full commercial operations, first…

11.1 Project Implementation Timeline

The project will be implemented over a 24-month period divided into two principal phases. Phase 1 (Months 0–12) encompasses all development activities including land acquisition, infrastructure construction, equipment procurement, and trial planting. Phase 2 (Months 12–24) transitions to full commercial operations, first harvest, and market entry.

Figure
gantt_chart.png — visualised from the accompanying data.

11.2 Key Milestones

Milestone Target Date Dependencies Status
Company Registration & Bank Account Month 1 Funding commitment Pending
Land Acquisition (Transfer) Month 3 Due diligence, title deed Pending
Water Use Licence Approved Month 4 DWS application Pending
EIA Record of Decision Month 4 Environmental assessment Pending
Irrigation Infrastructure Complete Month 8 Civil works, pump station Pending
Cold Storage Operational Month 10 Construction, commissioning Pending
Trial Planting (20 ha) Month 9 Irrigation, seedlings Pending
Full Commercial Planting (100 ha) Month 12 All infrastructure ready Pending
First Commercial Harvest Month 16 Crop maturity Pending
Export Market Entry Month 18 Certifications, logistics Pending
Phase 2 Expansion Planning Month 20 First season performance Pending

11.3 Critical Path Items

The following activities are on the critical path and any delays will directly impact the project timeline:

  1. Water use licence approval from the Department of Water and Sanitation (typically 3–6 months).

  2. Environmental Impact Assessment and Record of Decision from DFFE (typically 3–4 months).

  3. Irrigation infrastructure construction (5-month construction period, weather dependent).

  4. Seedling availability aligned to planting windows (seed must be ordered 6 months ahead).

  5. Cold storage commissioning prior to first harvest to avoid post-harvest losses.