RedHarvest Tomato Farms — Implementation Timeline

The following implementation schedule outlines the key milestones and deliverables for the first 36 months of the project, aligned with the phased development approach.

RedHarvest Tomato Farms (Pty) Ltd Business Plan › Implementation Timeline

Section 20 · Business Plan

Implementation Timeline

The following implementation schedule outlines the key milestones and deliverables for the first 36 months of the project, aligned with the phased development approach.

The following implementation schedule outlines the key milestones and deliverables for the first 36 months of the project, aligned with the phased development approach.

Period Milestone Key Deliverables
Months 1–3 Project Initiation Company registration; funding finalisation; land acquisition/lease; EIA submission; water licence application
Months 3–6 Phase 1 Infrastructure Land clearing; bulk water supply installation; reservoir construction; pump station and filtration
Months 6–9 Phase 1 Development Irrigation network (50 ha); packhouse construction; equipment procurement; seedling nursery
Months 9–12 Phase 1 First Harvest First planting cycle; first harvest; market agent appointments; packhouse commissioning
Months 12–18 Phase 2 Development Additional 40 ha land preparation and irrigation; cold room expansion; team scaling
Months 18–24 Phase 2 Full Production 90 ha under production; retail supply agreements secured; GlobalG.A.P. certification
Months 24–30 Phase 3 Development Final 30 ha land preparation and irrigation; processing contracts formalised
Months 30–36 Full Capacity 120 ha fully operational; all sales channels active; growth planning initiated