Verdant PhytoMed — Implementation Roadmap & Gantt Chart

The implementation plan below outlines the critical path from project inception to first export revenue. The plan has been structured around four sequential phases, with key milestones and dependencies identified. Total timeline from inception to first export shipment is estimated at 21–24…

Verdant PhytoMed (Pty) Ltd Business PlanSection 13 › Implementation Roadmap & Gantt Chart

Section 13 · Business Plan

Implementation Roadmap & Gantt Chart

The implementation plan below outlines the critical path from project inception to first export revenue. The plan has been structured around four sequential phases, with key milestones and dependencies identified. Total timeline from inception to first export shipment is estimated at 21–24…

The implementation plan below outlines the critical path from project inception to first export revenue. The plan has been structured around four sequential phases, with key milestones and dependencies identified. Total timeline from inception to first export shipment is estimated at 21–24 months.

13.1 Phase Summary

Phase Timeline Key Activities Budget (ZAR M) Milestone Dependencies
1. Licensing M0–M12 Legal setup, SAHPRA, EIA 12.0 Section 22C licence None
2. Construction M5–M17 Greenhouse, GMP facility 66.0 Facility complete Phase 1 progress
3. Certification M14–M20 GACP, GMP audits 8.0 EU-GMP certified Phase 2 complete
4. Production M17–M24 First harvest, export 34.0 First shipment All certifications

13.2 Gantt Chart

Figure
Gantt Chart — visualised from the accompanying data.

13.3 Critical Path & Key Milestones

Month Milestone Deliverable Owner Status Gate
M2 Company Incorporated CIPC Registration Certificate Legal Proceed
M6 EIA Approved Environmental Authorisation COO Proceed
M10 SAHPRA Licence Granted Section 22C Permit CEO Major Gate
M13 Greenhouse Complete Practical Completion Certificate COO Proceed
M17 GMP Facility Complete Construction Handover COO Proceed
M19 First Harvest Batch Release Certificate QA Proceed
M20 EU-GMP Certified Certificate of GMP Compliance CEO Major Gate
M21 Export Licence Issued DoH Export Permit Legal Proceed
M22 First Export Shipment Bill of Lading + COA COO Revenue Gate
M24 Phase 2 Planning Complete Expansion Business Case CFO Board Approval