VisionCare Specialist Eye Hospital — Implementation Roadmap

The phased implementation roadmap, the phase detail and dependencies, and the critical milestones from financial close through fit-out to commissioning and ramp-up.

VisionCare Specialist Eye Hospital Business PlanSection 9 › Implementation Roadmap

Section 9 · Business Plan

Implementation Roadmap

The phased implementation roadmap, the phase detail and dependencies, and the critical milestones from financial close through fit-out to commissioning and ramp-up.

The project follows a disciplined, four-phase implementation plan
spanning approximately 14 months from financial close to full surgical
go-live, with a defined Year-3 expansion. The Gantt chart below sets out
the critical path, key milestones and dependencies.

Figure 9.1
Figure 9.1 — Implementation roadmap and Gantt chart with critical milestones

9.1 Phase Detail & Dependencies

Phase 1 — Foundation (Months 0–4). Financial close
and shareholder agreements; company registration and the commencement of
HPCSA/Department of Health licensing; site lease and town-planning
approvals; architectural and CSSD-compliant theatre design; and
recruitment of the Medical Director and lead surgeons. Licensing and
site control are critical-path dependencies for all subsequent
construction.

Phase 2 — Build & Fit-out (Months 4–10).
Leasehold construction and theatre fit-out; medical-equipment
procurement and delivery (long-lead items ordered early); installation
of IT, EMR, PACS and networking; and construction of the optical
laboratory. Equipment delivery timelines and rand-linked import costs
are managed through early ordering and forward planning.

Phase 3 — Commissioning (Months 10–13). Equipment
installation and calibration; recruitment of nursing and
clinical-technologist staff; SAHPRA/OHSC accreditation and inspections;
medical-aid network contracting (designated-service-provider status);
and staff training with clinical SOP rollout. Accreditation is a hard
gate before any surgical activity.

Phase 4 — Launch & Ramp (Months 13+). Soft
launch of consultations and diagnostics, followed by full surgical
go-live; activation of marketing and the referral network; and the
structured ramp toward break-even utilisation. The Year-3 expansion
(fourth theatre and retina suite) is funded from internally-generated
cash.

9.2 Critical Milestones

Milestone Target (Months from Close) Dependency
Financial close & funding drawdown Month 0 Signed facility & equity agreements
Site lease & planning approval Month 4 Town-planning sign-off
Construction complete Month 10 Lease & design approval
OHSC/SAHPRA accreditation Month 13 Equipment install & SOPs
Soft launch (diagnostics) Month 13 Staff training complete
Full surgical go-live Month 14 Accreditation & scheme contracts
Break-even utilisation Month ~22 Referral-network maturity
Year-3 expansion complete Month ~24 Internal cash generation

Table 9.1 — Critical milestones, timelines and
dependencies

Confidential — this business plan is provided to prospective investors and lenders for evaluation purposes only and may not be reproduced or distributed without the written consent of VisionCare Specialist Eye Hospital (Pty) Ltd.