Project SunRise Oils — Implementation Roadmap

The phased delivery approach from mobilisation through build and commissioning to scale-up, the Gantt chart, the critical milestones, the critical path and project governance.

Project SunRise Oils Business PlanSection 9 › Implementation Roadmap

Section 9 · Business Plan

Implementation Roadmap

The phased delivery approach from mobilisation through build and commissioning to scale-up, the Gantt chart, the critical milestones, the critical path and project governance.

9.1 Phased Delivery Approach

The expansion programme is delivered in four sequenced phases over a
30-month horizon, structured to minimise execution risk, optimise
capital deployment, and ensure that revenue acceleration occurs
progressively as new capacity is commissioned. Each phase has a defined
gate review with the Investment Committee and key debt-financier
representatives, ensuring continuous oversight.

Phase 1 — Mobilisation (Months 0–7)

  • Funding close, legal documentation, security
    registration.
  • Site engineering, environmental impact assessment (EIA)
    submission and approval.
  • Equipment procurement and long-lead-time order placement
    (crushing line, refining tower, bottling lines).
  • Project Management Office (PMO) staff-up; engagement of EPCM
    contractor.
  • Commencement of farmer offtake contracting for the next harvest
    cycle.

Phase 2 — Build (Months 4–16)

  • Civil works for silo expansion, plant building, and bottling
    hall.
  • Installation of crushing line, solvent extraction unit, and
    desolventiser-toaster.
  • Installation of NBD refining plant.
  • Installation of two new bottling lines.
  • Solar PV array construction (8 MW, dual phase: 4 MW Months 6–10,
    4 MW Months 11–15).
  • Logistics and warehousing infrastructure ramp-up.

Phase 3 — Commissioning (Months 15–22)

  • Mechanical and process commissioning, site acceptance testing
    (SAT).
  • FSSC 22000 audit and certification refresh.
  • Pilot production batches, customer qualification trials.
  • Marketing and brand-launch programme for the consumer
    label.
  • Initial commercial production for crude oil and refined
    oil.

Phase 4 — Scale-up (Months 22–30)

  • Ramp to full nameplate capacity utilisation across all
    lines.
  • SADC export market activation (Botswana, Zimbabwe,
    Namibia).
  • Optimisation, debottlenecking, energy-intensity tuning.
  • Initiation of sustainability reporting cycle and integrated
    annual report.

9.2 Gantt Chart

Figure 16
Figure 16: Implementation roadmap — Gantt chart

9.3 Critical Milestones

Mo Milestone Phase Dependency / Risk
M0 Funding close & legal documentation Mobilisation Lender / equity sponsor diligence
M3 EIA approval Mobilisation Regulatory timeline; mitigation: pre-engagement
M5 Equipment supplier contracts placed Mobilisation OEM lead time 9–12 months
M9 Civil works substantially complete Build Weather, contractor capacity
M12 Crushing line installation complete Build Equipment delivery
M14 First crude oil production Build → Comm. Mechanical handover
M15 Refining tower mechanical handover Commissioning Skid integration
M16 Bottling lines mechanical handover Commissioning Packaging supply chain
M17 First refined oil pilot batch Commissioning QA sign-off
M19 FSSC 22000 audit complete Commissioning Audit body availability
M20 Brand launch into national retail Commissioning Listing approvals secured
M22 Full nameplate operating rate Scale-up Operational readiness
M24 First SADC export shipment Scale-up Distributor activation
M28 Steady-state Year 3 P&L profile Scale-up Demand realisation
M30 Programme close & lessons-learned Scale-up Final acceptance

9.4 Critical Path & Dependencies

The critical path runs from funding close (M0) through equipment
procurement (M3–M5), civil works (M4–M9), crushing line installation
(M8–M12), refining commissioning (M15–M19), and into commercial
production (M22). The longest single dependency is OEM equipment lead
time (9–12 months for the refining tower and 6–9 months for the crushing
line), which is mitigated by early order placement and dual-sourcing of
long-lead components.

9.5 Project Governance

A dedicated Project Management Office (PMO) is established at funding
close, reporting weekly to the COO and monthly to the Investment
Committee and lead lenders. The PMO maintains: (i) integrated project
schedule with weekly variance reporting, (ii) capital expenditure
tracking with monthly cost-to-complete forecasts, (iii) risk register
with owner-and-mitigation tracking, (iv) issue log, (v) supplier
performance scorecards, and (vi) stage-gate review documentation. An
independent Engineer (LEC) is appointed by the senior lenders to provide
construction-progress validation.

Confidential — this business plan is provided to prospective investors and lenders for evaluation purposes only and may not be reproduced or distributed without the written consent of Project SunRise Oils (Pty) Ltd.