Naledi Threads Business Plan — Implementation Plan

The timeline from lease signature to opening on 1 September 2026, covering fit-out, first buy, hiring and pre-opening marketing.

Implementation Plan

Jump to section
On this page

  • 10.1 Pre-opening timeline and gates
  • 10.2 Post-opening milestones
Implementation roadmap — pre-opening and the five-year build
Figure 12. Implementation roadmap — pre-opening and the five-year build.

10.1 Pre-opening timeline and gates

Week

Activity

Cash outflow

Gate — do not proceed without

–16 to –14

Company registration, bank account, funding applications

R6 000

Written loan approval in hand

–14 to –10

Site shortlist scored; landlord negotiation on rent, escalation and turnover clause

R0

Lease terms in writing, including the turnover breakpoint

–10

Lease signed with beneficial occupation secured

R35 530 deposit

Six to eight weeks rent-free confirmed in the lease

–10 to –7

Space plan, shopfit tender, contractor appointed

R12 000

Three quotations and a fixed-price contract

–9 to –4

Supplier accounts opened; CBD wholesale and cut-make-and-trim relationships built

R0

At least two accounts with credit terms agreed

–6

Opening range bought: 1 450 units, 55 styles, full size curve

R225 000

Written open-to-buy budget by category signed off

–6 to –2

Shopfit, electrical, air-conditioning, fitting rooms, signage

R417 000

Municipal signage approval and electrical certificate

–4 to –1

POS, inventory, CCTV, surveillance and card acquiring installed and tested

Included

A full test transaction cycle completed before opening

–3 to 0

Staff recruited, contracted and trained; UIF and COIDA registered

R26 000

Signed contracts above the minimum wage floor

–2 to 0

Stock received, tagged and merchandised; POPIA consent designed into the till process

R14 000

Every garment above R150 tagged before the doors open

0

Store opens, 1 September 2026

R34 000 launch

Business licence and Certificate of Acceptability where required

10.2 Post-opening milestones

Milestone

Timing

Consequence if missed

Trading density above R30 000 per m² annualised

Month 6

Review range and window; the position is wrong, not the price

Gross margin above 47% on completed months

Month 6

Markdown cadence is slipping; enforce the week-six rule

Creditor days above 28

Month 9

Cash trough deepens by roughly R11 700 for every four days missed

Cash never below R100 000

Month 10

Draw the standby overdraft; do not fund the gap from stock reduction

EBITDA after owner remuneration positive

Month 18

The Year 2 case does not hold; see the trigger points in Section 17

Debt service cover above 1.25x

Year 2

The loan covenant is at risk; approach the lender before the breach

Second consultant decision re-taken on evidence

Year 3

Do not hire on the plan; hire on the trading