VinoVista Estates — Implementation Timeline

The following implementation timeline illustrates the phased development of VinoVista Estates from incorporation through to full operational capacity:

VinoVista Estates (Pty) Ltd Business PlanSection 14 › Implementation Timeline

Section 14 · Business Plan

Implementation Timeline

The following implementation timeline illustrates the phased development of VinoVista Estates from incorporation through to full operational capacity:

14.1 Gantt Chart

The following implementation timeline illustrates the phased development of VinoVista Estates from incorporation through to full operational capacity:

Figure
Gantt Chart Chart — visualised from the accompanying data.

14.2 Key Milestones

Month Milestone Description
Month 1–2 Company Formation CIPC registration, SARS registration, bank accounts, legal framework
Month 2–5 Land Transfer Purchase agreement, conveyancing, water rights registration
Month 5–9 Phase 1 Planting 80 hectares cleared, prepared, trellised, and planted
Month 6–12 Winery Construction Crush pad, fermentation hall, barrel cellar built and equipped
Month 12–16 Tourism Build Tasting room and restaurant construction complete
Month 17–20 First Harvest Phase 1 grapes harvested (reduced first-year yield)
Month 20–22 Tourism Launch Tasting room and restaurant open to public
Month 22–24 Wine Launch First estate-bottled wines released to market
Month 24–28 Export Entry First export shipments to UK and German importers
Month 28–32 Phase 2 Harvest Phase 2 vines produce first commercial crop
Month 36 Full Operations All three revenue streams fully operational at scale