Streetfire Kitchens Business Plan — Implementation Roadmap
The phases from commissary fit-out and first three trucks to a five-truck fleet, dependencies, and the gate at each stage.
Implementation Roadmap
Jump to section
- Overview & contents
- i. Important Notice and Basis of Preparation
- 1. Executive Summary
- 2. The Operating Model
- 3. Licensing, Food Safety and Trading Rights
- 4. Market and Customers
- 5. SWOT and Competitive Position
- 6. Operations and Team
- 7. Financial Plan
- 8. Break-Even and Debt Service
- 9. Investment Analysis
- 10. Sensitivity and Scenario Analysis
- 11. Risk Analysis
- 12. Implementation Roadmap
- 13. Key Performance Indicators
- 14. Key Assumptions
- 15. Conclusion and Recommendation
- A. Appendix A: Consolidated Financial Summary
- B. Appendix B: Truck-Day and Trading Schedules
- C. Appendix C: Funding, Debt and Working Capital Schedules
- D. Appendix D: Risk Register
- E. Appendix E: Glossary
- 12.1 Development programme
- 12.2 Critical dependencies
- 12.3 Conditions precedent to drawdown
- 12.4 What each phase costs and what is recoverable
12.1 Development programme
|
Phase |
Months |
Activities |
Gate — do not proceed without |
|---|---|---|---|
|
1. Certify and secure |
1 to 7 |
Register the company; secure the commissary lease and zoning consent; fit out the commissary and obtain its Certificate of Acceptability first; complete Person in Charge and food handler training under Regulation 10 of R638; build or convert truck one with gas CoC, fire certificate and roadworthy; sign the first four weekday pitch agreements |
Commissary certified; truck one certified; four pitch agreements signed |
|
2. Prove one truck |
7 to 10 |
Trade truck one for a full quarter and count the covers; build the event portfolio with photography, references and set menus |
Average covers at or above 100 per service |
|
3. Build to three |
10 to 16 |
Commission trucks two and three; recruit and train crews; appoint the events and sales coordinator; secure weekend market roster places for the fleet |
Three trucks trading; event days above 8% of the calendar |
|
4. Fill the fleet |
Years 2 to 3 |
Lift utilisation toward 90%; drive event mix to 16%; commission truck four once pitch capacity is confirmed ahead of it |
Confirmed pitch capacity for a fourth truck; cover above 1.30x |
|
5. Reach five |
Years 4 to 5 |
Commission truck five; reach 98% utilisation; drive event days to 20% of the calendar |
Five trucks at 1 306 truck-days; cover above 3.0x |
12.2 Critical dependencies
|
Dependency |
What it gates |
Why it cannot be accelerated |
|---|---|---|
|
Commissary lease with zoning consent |
Everything |
The commissary is the premises most of the compliance sits against, and it must be certified before trucks are built |
|
Certificate of Acceptability, commissary |
Truck certification |
An Environmental Health Practitioner inspects the fixed premises first; a truck certificate follows the kitchen behind it |
|
Person in Charge training |
Any food handling at all |
Accredited training under Regulation 10 of R638; the certificate is issued in the individual’s name |
|
Four weekday pitch agreements |
Trucks two and three |
Weekday trade is 43.1% of revenue and pitches are granted at the discretion of others |
|
A full trading quarter on one truck |
The fleet |
Covers per service cannot be forecast into existence. Three months of real data is the only evidence that counts |
|
Events coordinator appointed |
The event mix |
Events are 30.1% of gross profit and grow from 11% to 20% of the calendar only with someone selling them |
|
Confirmed pitch capacity |
Each truck addition |
A truck without a pitch earns nothing and costs R134 000 a year to own |
|
Equity committed at drawdown |
Surviving the ramp |
Operations consume R2 361 370 across Years 1 and 2 while the fleet is still being built |
12.3 Conditions precedent to drawdown
12.4 What each phase costs and what is recoverable
|
Phase |
Cash committed |
Cumulative |
What is recoverable if the venture stops here |
|---|---|---|---|
|
1. Certify and secure |
R2 671 000 |
R2 671 000 |
One truck and the commissary equipment have a resale market; the fit-out in a leased building does not. The lease is the harder commitment |
|
2. Prove one truck |
R390 000 |
R3 061 000 |
A quarter of trading losses and the event portfolio. Nothing recoverable except the answer to the only question that matters |
|
3. Build to three |
R1 632 000 |
R4 693 000 |
Two more trucks, each with an active second-hand market. This is the point at which the fleet becomes a commitment |
|
4. Fill the fleet |
R2 259 000 |
R6 952 000 |
Trucks four and five are financed assets; the working capital consumed by the ramp is not |
|
5. Reach five |
R1 085 000 |
R8 037 000 |
A trading fleet with signed pitches, roster places and an event pipeline |
The shape of that table is why the second phase matters so far out of proportion to its cost. R390 000 buys a quarter of real trading data on one truck, at a point where the venture holds assets it could largely sell. The R4 976 000 committed after it is what converts a recoverable position into a fleet.