Savannah & Sakura Hospitality Group — Implementation Roadmap

The critical-path work packages and dependencies and the phased rollout underpinning SSHG's implementation.

Savannah & Sakura Hospitality Group Business PlanSection 9 › Implementation Roadmap

Section 9 · Business Plan

Implementation Roadmap

The critical-path work packages and dependencies and the phased rollout underpinning SSHG’s implementation.

The Group will be built over a phased 60-month programme that
sequences capital deployment, venue commissioning and revenue ramp to
manage execution risk and protect liquidity. Phasing is deliberate: the
Cape Town flagship and central production kitchen are commissioned first
to establish brand and operational foundations, followed by the estate,
the Johannesburg flagship, the academy, and finally Stellenbosch and the
national casual-dining rollout.

Figure 6
Figure 6. Five-year implementation Gantt chart across five workstreams, with key milestones.

9.1 Critical-Path Work Packages & Dependencies

The table below sets out the principal work packages, their
indicative timing and key dependencies. Items on the critical path —
brand and concept finalisation, the Cape Town flagship and the central
production kitchen — gate subsequent phases.

Work package Timing Key dependencies
Capital raise & financial close Months 1–6 Investor commitments; debt facilities agreed
Brand, concept & design finalisation Months 1–9 Financial close
Cape Town flagship build & launch Months 4–14 Brand finalisation; site secured (critical path)
Central production kitchen Months 4–12 Financial close (critical path)
Culinary academy establishment Months 8–20 Brand; partnerships; accreditation
Savannah Retreat estate development Months 6–26 Land acquisition; planning approvals
Johannesburg flagship Months 14–24 Cape Town flagship operational
Members’ club & consumer products launch Months 12–22 Flagship live; CRM & e-commerce stack
Stellenbosch flagship Months 24–36 Estate operational; brand scaled
National casual-dining rollout Months 24–60 Format proven; management depth
Advisory & franchising scale-up Months 30–60 Track record; IP codified

Table 7. Critical-path work packages, indicative
timing and dependencies.

9.2 Milestones & Capital Phasing

Capital is deployed in line with commissioning: R150m in Year 1,
R159m in Year 2 and R97m in Year 3, with the build programme
substantially complete by the end of Year 3. This phasing matches cash
outflows to revenue generation, limits peak funding requirements and
allows each phase to validate the model before the next is
committed.

Cape Town flagship live
M14
Johannesburg flagship live
M24
Retreat estate operational
M26
Three flagships trading
M36