AfricaFlame Flavors — Implementation Roadmap

The implementation roadmap spans 13 months from project initiation to grand opening, with a structured approach to ensure all critical workstreams are completed on time and within budget. The Gantt chart below illustrates the sequencing, dependencies, and duration of each major workstream.

AfricaFlame Flavors Business PlanSection 10 › Implementation Roadmap

Section 10 · Business Plan

Implementation Roadmap

The implementation roadmap spans 13 months from project initiation to grand opening, with a structured approach to ensure all critical workstreams are completed on time and within budget. The Gantt chart below illustrates the sequencing, dependencies, and duration of each major workstream.

10.1 Project Timeline and Milestones

The implementation roadmap spans 13 months from project initiation to grand opening, with a structured approach to ensure all critical workstreams are completed on time and within budget. The Gantt chart below illustrates the sequencing, dependencies, and duration of each major workstream.

Figure
Gantt Chart — visualised from the accompanying data.

10.2 Critical Milestones

Milestone Target Date Dependencies Status Criteria
Company Registration Month 1 None CIPC registration complete
Site Selection & Lease Month 3 Market research Lease signed, deposit paid
Liquor Licence Approved Month 5 Lease, zoning Licence issued by province
Construction Complete Month 10 Design, permits COC issued
Staff Fully Trained Month 11 Recruitment All positions filled, trained
Soft Opening Month 12 All systems live Invitation-only service
Grand Opening Month 13 Soft opening review Full public operations
Break-even Achieved Month 29 Revenue ramp-up Monthly EBITDA positive
Franchise Launch Month 48 Brand maturity First franchise agreement

10.3 Pre-Opening Budget

Pre-Opening Item Budget (ZAR) % of Total
Lease deposit and advance rent (3 months) 540,000 7.2%
Architectural design and permits 280,000 3.7%
Construction and fit-out 2,200,000 29.1%
Kitchen equipment and installation 1,500,000 19.9%
Furniture, fixtures, and decor 900,000 11.9%
Technology and POS systems 450,000 6.0%
Pre-opening staff salaries (3 months) 410,000 5.4%
Marketing and launch campaign 850,000 11.3%
Licensing, permits, legal fees 250,000 3.3%
Working capital reserve 170,000 2.3%
TOTAL PRE-OPENING INVESTMENT 7,550,000 100%
Figure
Startup Costs — visualised from the accompanying data.

This document contains proprietary and confidential information. Distribution without written consent is prohibited.