BuildMart — Implementation Roadmap

The critical path and key milestones from inception to a 32-store national footprint over the seven-year horizon.

BuildMart Business PlanSection 15 › Implementation Roadmap

Section 15 · Business Plan

Implementation Roadmap

The critical path and key milestones from inception to a 32-store national footprint over the seven-year horizon.

15.1 Critical Path &
Milestones

The implementation plan is structured around a 24-month critical path
from company incorporation to the opening of the fifth store. The Gantt
chart below illustrates the key workstreams, their interdependencies,
and milestone dates. Each workstream is assigned an executive sponsor
and dedicated project manager, with weekly progress reporting to the
Steering Committee.

Figure 10
Figure 10: Gantt

15.2 Key Milestones

Milestone Target Date Dependency Owner
Company Registration & CIPC Month 1 None CEO / Legal
Financing Close Month 3 Business plan approval CFO
Site Acquisition (Store 1 & 2) Month 5 Financing close COO
ERP System Go-Live Month 6 Vendor selection (M2) CTO
Distribution Centre Operational Month 8 Site acquisition, equipment COO
Store 1 Grand Opening (JHB) Month 10 Fit-out, recruitment, stock COO
Store 2 Grand Opening (PTA) Month 12 Fit-out, recruitment, stock COO
E-commerce Platform Launch Month 12 ERP integration CTO
Store 3 Grand Opening (DBN) Month 15 Phase 2 site acquisition COO
Private-Label Product Launch Month 18 Supplier agreements, SABS CCO
Store 4 Grand Opening (CPT) Month 17 Site acquisition COO
Store 5 Grand Opening (EL) Month 19 Site acquisition COO
Performance Review & Phase 2 Plan Month 24 12 months trading data CEO