KwaCrete Ready Mix — Implementation Roadmap

The phased plan, the Gantt chart, the critical path and dependencies, the key milestones and the first-100-days priorities from financial close through plant commissioning.

KwaCrete Ready Mix Business PlanSection 9 › Implementation Roadmap

Section 9 · Business Plan

Implementation Roadmap

The phased plan, the Gantt chart, the critical path and dependencies, the key milestones and the first-100-days priorities from financial close through plant commissioning.

This section sets out the phased plan to take KwaCrete from financial
close to a steady-state, cash-generative operation. The roadmap is
organised into four phases — Mobilise, Build, Launch and Operate —
spanning approximately 24 months, with critical milestones, dependencies
and accountabilities defined. The sequencing reflects the long-lead
nature of plant procurement and the regulatory steps that must precede
commissioning.

9.1 Phased Plan

Each phase has a clear objective and exit criteria. The plan is
deliberately conservative on timing, building in contingency for
procurement lead times, regulatory approvals and commissioning, all of
which are common sources of slippage in plant projects.

Phase Months Objective Exit criteria
1. Mobilise M0–M5 Close funding, secure site, obtain approvals Capital drawn; site leased; permits in hand
2. Build M3–M10 Procure & erect plant, fleet, lab; recruit & train Plant erected; fleet delivered; team in place
3. Launch M10–M14 Commission, certify, win first contracts SANS 878 certified; first commercial pour
4. Operate M13–M24+ Ramp volume to break-even and beyond Cash break-even run-rate achieved

Table 9.1 — Implementation phases and exit criteria.

9.2 Gantt Chart

The Gantt chart below maps the detailed work-streams across the
implementation timeline, highlighting the critical path and the four key
milestones: financial close, plant commissioning, first commercial pour,
and the break-even run-rate.

Figure 9.1
Figure 9.1 — Implementation Gantt chart with phases and key milestones (months from financial close).

9.3 Critical Path & Dependencies

The critical path runs through funding close, plant procurement and
erection, commissioning and certification. Several dependencies are
decisive for on-time delivery:

  • Funding close gates everything. No long-lead
    orders can be placed until capital is committed; this is the first and
    most important milestone.
  • Plant procurement is the longest lead.
    Batching-plant manufacture and delivery drive the build timeline;
    ordering early in M3 is essential.
  • Civil works depend on the site and approvals.
    Site preparation cannot begin before the lease and environmental
    authorisation are secured.
  • Certification precedes first pour. SANS 878
    certification must be achieved before commercial supply, particularly
    for public and tier-one work.
  • Supplier contracts must be in place before
    commissioning.
    Cement and aggregate agreements are required for
    trial batches and the production ramp.

9.4 Key Milestones

Milestone Target Significance
Financial close Month 3 Capital committed; long-lead procurement unlocked
Plant commissioned Month 12 Plant operational; trial batches complete
First commercial pour Month 14 Revenue generation begins; certification achieved
Cash break-even run-rate Month 22 Monthly operations self-funding
Full ramp / second shift Month 24+ Capacity scale-up toward practical ceiling

Table 9.2 — Key milestones and their significance.

9.5 First-100-Days Priorities

Immediately following financial close, management will focus on the
actions that most de-risk the build: finalising the plant-supply
contract, confirming the site lease and lodging the environmental
application, opening cement-supplier negotiations, and recruiting the
Plant & Logistics Manager so that operational ownership of the build
is established early. Disciplined execution of these first-100-day
priorities is the single greatest determinant of an on-time, on-budget
commissioning.