ProNutri Dairy Foods — Implementation Plan and Timeline

The implementation timeline spans an 18-month pre-operations phase from financial close to the commencement of commercial production. The critical path runs through environmental approvals, building construction, equipment procurement and installation, and HACCP certification. The Gantt chart below illustrates the sequencing and interdependencies…

ProNutri Dairy Foods (Pty) Ltd Business PlanSection 15 › Implementation Plan and Timeline

Section 15 · Business Plan

Implementation Plan and Timeline

The implementation timeline spans an 18-month pre-operations phase from financial close to the commencement of commercial production. The critical path runs through environmental approvals, building construction, equipment procurement and installation, and HACCP certification. The Gantt chart below illustrates the sequencing and interdependencies…

The implementation timeline spans an 18-month pre-operations phase from financial close to the commencement of commercial production. The critical path runs through environmental approvals, building construction, equipment procurement and installation, and HACCP certification. The Gantt chart below illustrates the sequencing and interdependencies of key implementation milestones.

15.1 Implementation Gantt Chart

Figure
Gantt Chart — visualised from the accompanying data.

15.2 Key Milestones

Milestone Target Date Dependency
Financial Close Month 1 Completion of due diligence and legal agreements
Environmental Impact Assessment Approved Month 6 DFFE approval of EIA application
Building Construction Complete Month 12 Site preparation and civil works
Major Equipment Delivered and Installed Month 15 Import logistics and installation
HACCP Certification Obtained Month 17 Facility completion and QA documentation
Trial Production Complete Month 17 Equipment commissioning and product testing
Commercial Production Commences Month 18 All regulatory approvals and customer contracts
Break-Even (Monthly Cash Flow) Month 32 14 months post commercial start
Phase 2 Capacity Expansion Initiated Month 30 Subject to demand and funding availability

This document contains proprietary and confidential information. Distribution without written consent is prohibited.