So Cool Juice Co. — Implementation Roadmap
The implementation plan follows a phased approach progressing from establishment through to commercial production within 9 months, with a 24-month roadmap detailing all critical milestones, dependencies, and workstreams.
Section 11 · Business Plan
Implementation Roadmap
The implementation plan follows a phased approach progressing from establishment through to commercial production within 9 months, with a 24-month roadmap detailing all critical milestones, dependencies, and workstreams.
The implementation plan follows a phased approach progressing from establishment through to commercial production within 9 months, with a 24-month roadmap detailing all critical milestones, dependencies, and workstreams.
Figure 11.1: Implementation Roadmap — Gantt Chart. Vertical dashed line marks Commercial Production Start at Month 9.
11.1 Phase 1: Foundation (Months 0–4)
-
Company registration, food manufacturing licences, environmental impact assessment.
-
Facility lease, architectural planning, cold room construction, and processing area fit-out.
-
Equipment procurement from leading suppliers (JBT, Tetra Pak, GEA, Hiperbaric for HPP).
-
Key leadership recruitment: Operations Director, Food Technologist, Quality Manager.
11.2 Phase 2: Build-Out (Months 4–9)
-
Equipment installation, commissioning, and operator training.
-
FSSC 22000 / HACCP certification audit preparation and execution.
-
Fruit supplier agreements finalised with 15+ farms across Western Cape.
-
Pilot production: 50,000–100,000 litres for quality validation and shelf-life testing.
-
Brand identity finalisation, packaging design, and marketing material production.
-
Retail buyer presentations and listing negotiations with Woolworths, Checkers, Pick n Pay.
11.3 Phase 3: Commercial Operations (Months 9–24)
-
Full commercial production at Month 9, targeting 300,000 litres/month (60% utilisation).
-
Progressive ramp to 80% by Month 15 and 95% by Month 24.
-
E-commerce platform launch at Month 10 with Takealot and own website.
-
SADC export market entry from Month 15 targeting Namibia and Botswana.
-
Phase 2 expansion feasibility and capex planning from Month 18.