Tiptop Market — Implementation Plan & Timeline
The pre-launch period is estimated at 9 months across four phases: Formation & Funding, Technology & Infrastructure, People & Go-to-Market, and Launch & Expansion.
Section 13 · Business Plan
Implementation Plan & Timeline
The pre-launch period is estimated at 9 months across four phases: Formation & Funding, Technology & Infrastructure, People & Go-to-Market, and Launch & Expansion.
The pre-launch period is estimated at 9 months across four phases: Formation & Funding, Technology & Infrastructure, People & Go-to-Market, and Launch & Expansion.
Figure 13.1: Implementation Gantt Chart
Phase 1: Formation & Funding (M0–3)
CIPC registration, SARS registration, legal structuring, shareholder agreements, Series A completion, board formation, bank accounts, IP registration.
Phase 2: Technology & Infrastructure (M1–8)
Core platform development (agile, 2-week sprints), warehouse lease and fit-out, WMS procurement, payment gateway integration (Peach Payments, PayFast), logistics contracting.
Phase 3: People & GTM (M3–9)
75-person team recruitment, seller onboarding programme launch, pre-launch marketing, 500-user beta testing, load and security penetration testing.
Phase 4: Launch & Expansion (M9+)
Public launch, seller onboarding acceleration, JHB warehouse (M14–18), DBN hub (M18–22), loyalty programme (M12), Series B assessment (M24).