Mainstreet Brick Business Plan — Implementation Timeline

The timeline from funding close to full production, covering site works, plant installation, commissioning and first sales.

Implementation Timeline

Jump to section
Implementation roadmap — feasibility to commercial production
Figure 23. Implementation roadmap — feasibility to commercial production.

Phase

Months

Key activities

Capital committed

1. Feasibility and site securing

0–3

Catchment demand study; competitor and pricing survey; site identification and lease option; aggregate supply quotations; cement supply negotiation

Study costs and option fee only

2. Approvals and funding

3–8

Zoning confirmation and environmental authorisation under NEMA; water use registration; development finance application and credit approval; equipment finance approval; equity drawn

Professional fees of approximately R520 000

3. Pre-sales

5–11

Sales manager appointed; merchant and contractor agreements negotiated; sample batch produced on the supplier demonstration plant; target 40 to 50% of capacity contracted

Sales overhead

4. Construction and installation

8–13

Yard preparation and hardstand; power and water connection; machine, batching plant and silo installation; commissioning and operator training

Bulk of capital expenditure

5. Trial production and certification

13–15

Trial batches, mix optimisation, SANS 1215 strength verification, first customer deliveries

Opening inventory of R950 000

6. Commercial production and ramp

15–27

Year 1 of the model; capital moratorium period; monthly funder reporting; the three operational disciplines embedded from the first month

Working capital

18.1 Gates and critical dependencies

Gate

When

Condition

Consequence if not met

Gate 1: the demand study supports the plant

Month 3

Independent catchment study confirming masonry consumption within 100 km sufficient to absorb output at the modelled share, with named competitor capacity mapped

Do not exercise the site option. The study cost is the entire loss and it is the cheapest possible outcome

Gate 2: approvals and credit secured

Month 8

Zoning granted, environmental authorisation issued, development finance credit approved

Do not draw equity or order equipment. Neither approval is within the developer’s control

Gate 3: offtake contracted

Month 11

40 to 50% of capacity covered by signed merchant, development or housing programme agreements

Do not draw construction capital. Break-even above 80% of capacity makes an uncontracted ramp unfundable

Gate 4: commissioning and certification

Month 15

SANS 1215 strength verified at the modelled cement dosage; operators trained; wet mix optimised

Do not begin commercial deliveries. A plant that certifies late loses the accounts it pre-sold

Gate 5: cash break-even crossed

Month 27

Utilisation above 78% with cover above 1.05 times

Invoke the trigger points in Section 17.3 rather than waiting for the annual accounts