Mainstreet Brick Business Plan — Implementation Timeline
The timeline from funding close to full production, covering site works, plant installation, commissioning and first sales.
Implementation Timeline
Jump to section
- Overview & contents
- i. Important Notice and Basis of Preparation
- 1. Executive Summary
- 2. The Unit Economics of Brick Making
- 3. Market Analysis
- 4. Products and Positioning
- 5. SWOT and Competitive Position
- 6. Site, Plant and Production
- 7. Route to Market and Sales Strategy
- 8. Regulatory, Environmental and Quality Compliance
- 9. Management and Organisation
- 10. Capital Requirement and Funding
- 11. Financial Projections
- 12. Break-Even Analysis
- 13. Debt Service and Working Capital
- 14. Investment Returns
- 15. Sensitivity and Scenario Analysis
- 16. Value Creation Levers
- 17. Risk Management
- 18. Implementation Timeline
- 19. Conditions for Success and Exit Options
- 20. Key Performance Indicators
- 21. Key Assumptions
- 22. Conclusion
- A. Appendix A: Consolidated Financial Summary
- B. Appendix B: Capital and Depreciation Schedules
- C. Appendix C: Funding and Debt Schedules
- D. Appendix D: Risk Register
- E. Appendix E: Glossary
|
Phase |
Months |
Key activities |
Capital committed |
|---|---|---|---|
|
1. Feasibility and site securing |
0–3 |
Catchment demand study; competitor and pricing survey; site identification and lease option; aggregate supply quotations; cement supply negotiation |
Study costs and option fee only |
|
2. Approvals and funding |
3–8 |
Zoning confirmation and environmental authorisation under NEMA; water use registration; development finance application and credit approval; equipment finance approval; equity drawn |
Professional fees of approximately R520 000 |
|
3. Pre-sales |
5–11 |
Sales manager appointed; merchant and contractor agreements negotiated; sample batch produced on the supplier demonstration plant; target 40 to 50% of capacity contracted |
Sales overhead |
|
4. Construction and installation |
8–13 |
Yard preparation and hardstand; power and water connection; machine, batching plant and silo installation; commissioning and operator training |
Bulk of capital expenditure |
|
5. Trial production and certification |
13–15 |
Trial batches, mix optimisation, SANS 1215 strength verification, first customer deliveries |
Opening inventory of R950 000 |
|
6. Commercial production and ramp |
15–27 |
Year 1 of the model; capital moratorium period; monthly funder reporting; the three operational disciplines embedded from the first month |
Working capital |
18.1 Gates and critical dependencies
|
Gate |
When |
Condition |
Consequence if not met |
|---|---|---|---|
|
Gate 1: the demand study supports the plant |
Month 3 |
Independent catchment study confirming masonry consumption within 100 km sufficient to absorb output at the modelled share, with named competitor capacity mapped |
Do not exercise the site option. The study cost is the entire loss and it is the cheapest possible outcome |
|
Gate 2: approvals and credit secured |
Month 8 |
Zoning granted, environmental authorisation issued, development finance credit approved |
Do not draw equity or order equipment. Neither approval is within the developer’s control |
|
Gate 3: offtake contracted |
Month 11 |
40 to 50% of capacity covered by signed merchant, development or housing programme agreements |
Do not draw construction capital. Break-even above 80% of capacity makes an uncontracted ramp unfundable |
|
Gate 4: commissioning and certification |
Month 15 |
SANS 1215 strength verified at the modelled cement dosage; operators trained; wet mix optimised |
Do not begin commercial deliveries. A plant that certifies late loses the accounts it pre-sold |
|
Gate 5: cash break-even crossed |
Month 27 |
Utilisation above 78% with cover above 1.05 times |
Invoke the trigger points in Section 17.3 rather than waiting for the annual accounts |