Mainstreet Brick Business Plan — Appendix D: Risk Register
Detailed risk register scoring likelihood and impact across market, operational, financial and environmental risks.
Appendix D: Risk Register
Jump to section
- Overview & contents
- i. Important Notice and Basis of Preparation
- 1. Executive Summary
- 2. The Unit Economics of Brick Making
- 3. Market Analysis
- 4. Products and Positioning
- 5. SWOT and Competitive Position
- 6. Site, Plant and Production
- 7. Route to Market and Sales Strategy
- 8. Regulatory, Environmental and Quality Compliance
- 9. Management and Organisation
- 10. Capital Requirement and Funding
- 11. Financial Projections
- 12. Break-Even Analysis
- 13. Debt Service and Working Capital
- 14. Investment Returns
- 15. Sensitivity and Scenario Analysis
- 16. Value Creation Levers
- 17. Risk Management
- 18. Implementation Timeline
- 19. Conditions for Success and Exit Options
- 20. Key Performance Indicators
- 21. Key Assumptions
- 22. Conclusion
- A. Appendix A: Consolidated Financial Summary
- B. Appendix B: Capital and Depreciation Schedules
- C. Appendix C: Funding and Debt Schedules
- D. Appendix D: Risk Register
- E. Appendix E: Glossary
|
Risk |
Impact |
Mitigation |
Owner |
|---|---|---|---|
|
Price war with an established local plant |
Critical — a 7.5% price fall takes the project return from 15.5% to minus 27.3%. An incumbent with written-down equipment can sustain a discount indefinitely against a start-up carrying R20.21m of new debt. |
Compete on SANS certification and delivery reliability, never on price; contracted offtake of 40 to 50% before commissioning; a defined exit trigger agreed in writing at entry. |
Managing director |
|
Cement price escalation |
Critical — cement is 29% of revenue from a concentrated supplier group and a 15% increase takes the return to minus 1.8%. Energy and carbon costs have historically been passed through. |
Volume-based bulk supply agreement with a cap or notice period, negotiated before commissioning; dosage at specification; grow the block share where price carries the input. |
Managing director |
|
Sales volume shortfall and a slow ramp |
High — cash break-even is 67.3% of capacity in Year 1 against a planned 66.0%. A 15% volume shortfall takes the return to minus 1.8%. |
Sales manager appointed six months ahead of production; sample batch from the supplier demonstration plant; 40 to 50% of capacity contracted before construction capital is drawn. |
Sales manager |
|
Licensing, rezoning or environmental delay |
High — interest accrues with no revenue. Industrial zoning and NEMA authorisation take three to nine months each and neither is within the developer’s control. |
Conditional site option rather than purchase; only study and professional fees committed until both are granted; development finance application lodged in parallel. |
Managing director |
|
Construction and equipment cost overrun |
Medium-high — a 15% overrun costs roughly two points of return on a project that clears its hurdle by none. |
Fixed-price equipment and installation quotations with performance guarantees on output rate and unit quality; retention held until proven production. |
Managing director |
|
Contractor insolvency and bad debt |
Medium-high — a single R400 000 default in Year 1 consumes a fifth of that year’s EBITDA. The plan carries a 1.5% provision as a deliberate charge. |
Credit vetting before first delivery; individual limits set against observed offtake; system-enforced stop-supply; credit insurance on concentrated accounts; cash-and-merchant weighting during the ramp. |
Finance manager |
|
Debtor days stretching beyond 40 |
Medium — one day is R174 000 at Year 5 revenue, and a drift to 50 days absorbs R1.74m and exhausts the committed facility. |
Credit control treated as treasury rather than administration; monthly ageing review; stop-supply on all accounts beyond terms. |
Finance manager |
|
Breakage and reject rate above plan |
Medium — each percentage point is R540 722 of revenue at Year 3 volumes, more than any commercial initiative in this plan. |
Handling training, curing control, pallet condition, stacking discipline and a daily reject count reconciled to production. |
Production manager |
|
Cement over-dosing |
Medium — every 1% of excess cement costs R152 177 a year at Year 3 volumes. |
Properly graded aggregate, calibrated batching, and a strength testing regime that gives the confidence to run at specification rather than above it. |
Production manager |
|
Machine downtime |
Medium — the plant has a single production line and no redundancy. |
Planned maintenance schedule, critical spares held on site, and a service agreement with the equipment supplier. |
Production manager |
|
Aggregate supply disruption or haul cost |
Medium — aggregate is the highest-tonnage input and every kilometre is a permanent cost. |
Dual supply quotations with delivered pricing; the site located between the quarry and the demand centre. |
Managing director |
|
SANS 1215 certification lapse |
Medium — certification is the entire basis of the specified-supplier position and the barrier that excludes the informal sector. |
Batch testing without exception; laboratory technician appointed before commissioning; certificate file retained for buyer diligence. |
Quality technician |