Solstice Energy — Implementation Roadmap

The project timeline, critical milestones and construction programme from financial close to commercial operation.

Solstice Energy Business PlanSection 11 › Implementation Roadmap

Section 11 · Business Plan

Implementation Roadmap

The project timeline, critical milestones and construction programme from financial close to commercial operation.

11.1 Project Timeline

The project implementation spans approximately 30 months from project
inception to commercial operation date (COD), with the critical path
running through environmental authorisation, grid connection approval,
financial close, and construction completion. The timeline has been
structured to align with REIPPPP procurement cycles and incorporates
reasonable contingency allowances for each phase.

Figure 7
Figure 7: Implementation Roadmap — Gantt Chart

11.2 Critical Milestones

Milestone Target Date Dependencies Phase
Project Company Formation Month 1–2 Legal advisors, shareholder agreement Development
Site Secured (Lease/Purchase) Month 2–5 Due diligence, zoning confirmation Development
EIA Submission Month 3 Specialist studies, public participation Development
Grid Connection Application Month 3 Cost estimate letter from Eskom Development
Generation License Filed Month 4 NERSA application, technical compliance Development
PPA Execution Month 6–13 REIPPPP bid award or corporate PPA Development
Financial Close Month 14–16 All conditions precedent satisfied Financial
EPC Contract Award Month 14–16 Competitive tender, due diligence Construction
Construction Commencement Month 16 Site mobilisation, permits in place Construction
Module Installation Complete Month 26 EPC progress, quality assurance Construction
Grid Energisation Month 28 Eskom connection, protection tested Commissioning
Commercial Operation Date Month 30–31 Performance tests passed, NERSA approval Operations

Table 8: Critical Milestones and Dependencies

11.3 Construction Programme

The construction phase spans approximately 14–16 months from site
mobilisation to commercial operation, executed under a fixed-price,
date-certain Engineering, Procurement, and Construction (EPC) contract
with a Tier 1 international EPC contractor experienced in South African
utility-scale solar projects. The EPC contract will include
comprehensive performance guarantees covering minimum energy yield,
system availability, and completion date, with liquidated damages for
underperformance providing financial protection to the project company
and its lenders.

The construction programme is sequenced as follows: civil works and
foundations (Months 16–22) including access roads, fencing, cable
trenches, and tracker foundations; mounting structure and module
installation (Months 20–26) representing the most labour-intensive phase
with 350–500 construction workers; electrical and inverter installation
(Months 22–27) including DC cabling, inverter stations, and MV
collection network; grid connection and substation (Months 24–28)
including the 33/132 kV transformer and transmission line; and testing
and commissioning (Months 27–30) including individual system testing,
integrated system testing, performance guarantee testing, and grid code
compliance testing.