KarooPrime Capretto — Implementation Roadmap
The phased implementation roadmap, the key milestones and the critical path from financial close through commissioning to steady-state throughput.
Section 9 · Business Plan
Implementation Roadmap
The phased implementation roadmap, the key milestones and the critical path from financial close through commissioning to steady-state throughput.
The build-out follows a disciplined, gated sequence. Phase 1 proves
the integrated unit economics of a single hub; Phase 2 replicates
regionally and unlocks export; Phase 3 scales the farmer network and
value-added capacity to steady state. Capital is released against the
achievement of operational milestones rather than on a fixed
schedule.
9.1 Critical milestones and dependencies
| Milestone | Description | Target | Depends on |
|---|---|---|---|
| Financial close | Phase-1 funding committed and drawn | Q1–Q2 Yr1 | — |
| Plant live | Abattoir commissioned; commercial slaughter begins (40k run-rate) | Q8 (end Yr2) | Construction, certification |
| First export | Export accreditation and first Halaal export consignment | Yr3 | Plant live, certification |
| Phase-3 live | Second capacity expansion commissioned | Yr5–Yr6 | Phase-2 throughput proof |
| Steady state | 400k head p.a.; 10,000+ farmers contracted | Yr7 | All prior phases |
Table 9.1 — Critical-path milestones and dependencies.
Confidential — this business plan is provided to prospective investors and lenders for evaluation purposes only and may not be reproduced or distributed without the written consent of KarooPrime Capretto (Pty) Ltd.