KarooPrime Capretto — Implementation Roadmap

The phased implementation roadmap, the key milestones and the critical path from financial close through commissioning to steady-state throughput.

KarooPrime Capretto Business PlanSection 9 › Implementation Roadmap

Section 9 · Business Plan

Implementation Roadmap

The phased implementation roadmap, the key milestones and the critical path from financial close through commissioning to steady-state throughput.

The build-out follows a disciplined, gated sequence. Phase 1 proves
the integrated unit economics of a single hub; Phase 2 replicates
regionally and unlocks export; Phase 3 scales the farmer network and
value-added capacity to steady state. Capital is released against the
achievement of operational milestones rather than on a fixed
schedule.

Figure 9.1
Figure 9.1 — Implementation roadmap and critical path across the seven-year horizon, showing phase bands, task durations, dependencies and key milestones.

9.1 Critical milestones and dependencies

Milestone Description Target Depends on
Financial close Phase-1 funding committed and drawn Q1–Q2 Yr1
Plant live Abattoir commissioned; commercial slaughter begins (40k run-rate) Q8 (end Yr2) Construction, certification
First export Export accreditation and first Halaal export consignment Yr3 Plant live, certification
Phase-3 live Second capacity expansion commissioned Yr5–Yr6 Phase-2 throughput proof
Steady state 400k head p.a.; 10,000+ farmers contracted Yr7 All prior phases

Table 9.1 — Critical-path milestones and dependencies.