GreenH2 Fertiliser — Implementation Roadmap
The critical milestones and dependencies and the phased critical path from the seed round through construction to first output.
Section 9 · Business Plan
Implementation Roadmap
The critical milestones and dependencies and the phased critical path from the seed round through construction to first output.
The roadmap below sets out the critical path from inception to full
production, with milestones, dependencies and the five workstreams that
must be sequenced to reach financial close and commercial operation.
Development approvals and FEED run in parallel and gate financial close;
EPC construction is the longest pole; commissioning and ramp follow
mechanical completion.
9.1 Critical milestones & dependencies
Table 8. Key milestones, target timing and
principal dependencies.
| Milestone | Target | Principal dependency |
|---|---|---|
| Environmental authorisation | Year 2 | EIA completion and public participation |
| FEED & cost estimate | Year 2 | Engineering studies and technology licensing |
| Offtake ≥ 60% contracted | Year 2–3 | Commercial negotiations with anchor buyers |
| Financial close | Year 2–3 | Permits, offtake, equity syndication, debt commitment |
| Construction start | Year 3 | Financial close and EPC mobilisation |
| Mechanical completion | Year 4–5 | EPC delivery of all process units |
| Commercial operation (COD) | Year 4 | Commissioning and performance testing |
| Full production (100%) | Year 6 | Successful ramp and reliability runs |